●To connect the load with the UPS, please turn off all the loads first, then perform the connection and finally turn on the loads one by one.
●No matter the UPS is connected to the utility power or not, the output of the UPS may have electricity. The parts inside the unit may still have hazardous voltage after turning off the UPS. To make the UPS have no output, power off the UPS, and then disconnect the utility power supply.
●Suggest charging the batteries for 8 hours before use. After connection, turn the bypass breaker in the “ON” position, the UPS will charge the batteries automatically. You can also use the UPS immediately without charging the batteries first, but the backup time may be less than the standard value.
●If it is necessary to connect the inductance load such as a monitor or a laser printer to the UPS, the
Input and output Terminal Block wiring diagram of 6000L(XL)/10000L(XL)
Important notes: If the UPS is used in single mode, JPI and JP2 must be connected by 10AWG(6mm2). If the UPS is used in parallel mode, the Jumper between JP1 and JP2 must be removed
7