Daniel 3818 LNG Liquid Ultrasonic Meter Installation Manual | Section 3: Electrical installation | |
May 2012 | ||
|
|
|
3.6.9Sealing the unit
The unit should be properly sealed with a sealing compound after electrical connections have been tested according to the customer's Best Practices schedule. Some areas require a witnessed Acceptance Test for the installed system and require that the meter run for a predetermined length of time (approximately one to two weeks) before the unit is sealed. This allows time to verify all electrical connections are correct, that the meter is accurately measuring flow and that the meter meets the customer’s installation requirements.
Sealing the unit | 57 |