Section 4: Configuring a 3818 LNG Meter | Daniel 3818 LNG Liquid Ultrasonic Meter Installation Manual |
May 2012 | |
|
|
Procedure
1.Remove electrical power to the meter. If installed, remove the endcap security latches and seals and then, remove the endcap.
2.Refer to the Field Communicator Users Manual wiring diagrams and commissioning instructions provided with your handheld device. Register the product to activate the end user license.
3.Fully charge the Field Communicator battery prior to use. Important: Do not change the battery in a hazardous area environment. The power supply is not intrinsically safe
4.On the meter, run the wires through the field wiring conduit and into the transmitter electronics enclosure.
FigureA.
A. Field wiring conduit entries (8)78 | Using a Field Communicator to configure the meter |