Installation
2.4.2Rack Installation
NOTE
• When the Liebert® GXT3™ is installed in a rack, it must be supported by a shelf, fixed rails or slide rails on each side. The
•Mounting hardware and slide rails are sold separately. Contact your local Emerson representative for these options and any assistance.
•
To install a Liebert GXT3 rack/tower UPS in a rack:
1.Unpack the two slide rails assemblies and mounting hardware from the
Slide rail assembly includes inner member and front and rear members. They are interchange- able between
2.Remove inner member of each slide rail assembly by extending it to its outermost position, depressing the retaining latch and then pulling inner member from slide rail assembly (see Figure 11).
Figure 11 Pulling inner member from each slide rail assembly
|
|
| t |
|
|
| u |
|
| o | |
| l |
| |
l |
| ||
u |
|
| |
P |
|
|
|
Slide rail assembly
Retaining latch
Inner member
3. Determine the Liebert GXT3’s mounting position inside the racks vertical rails.
! CAUTION
Reduce the risk of tipping the rack by installing the Liebert GXT3 as low as possible in the rack.
4.Attach the rear member of each slide rail assembly to the rack’s rails with two
Figure 12 Installing rear member of each slide rail assembly
Vertical pole |
M5 screw (4 pcs) |
Rear member |
Front member |