25613-0-0309 Page 33
Installing Support Brackets (Figure 49)
A horizontal pipe support MUST BE used for each 3 feet of horizontal
run. The pipe supports should be placed around the pipe and nailed
in place to framing members. There MUST BE a 3 inch clearance
to combustibles above ue pipe and elbows and 1 inch clearance
on both sides and bottom of the ue pipe to combustibles on all
horizontal pipe sections and elbows.
Vertical runs of this vent systems must be supported every 4 feet
above the appliance ue outlet by wall brackets attached to the
vent pipe and secured with nails or screws to structural framing
members.
Figure 49
Installing Firestops (Figures 50, 51, 52, and 53)
Firestops are required for safety whenever the vent system passes
through an interior wall, an exterior wall, or a ceiling. These restops
act as a rebreak heat shield and as a means to insure that minimum
clearances are maintained to the vent system.
Horizontal runs in the vent system which pass through either interior
or exterior walls, require the use of wall restops on both sides of
the wall through which the vent passes.
Cut an appropriate sized hole in wall. See Figure 50. Position
restop on interior side of wall for hole.
Attention: Wall restop hole is off-set towards bottom of wall
opening. Secure with nails or screws. Continue the vent run through
the restop. See Figure 50.
Figure 50
Vertical runs of this system which pass through ceilings require the
use of ONE (1) ceiling restop at the hole in each ceiling through
which the vent passes.
Position a plumb bob directly over the center of the vertical vent
component and mark the ceiling to establish the center point of the
vent. Drill a hole or drive a nail through this center point and check
the oor above for any obstructions such as wiring or plumbing
runs. Reposition the appliance and vent system, if necessary, to
accommodate ceiling joists and/or obstructions.
Cut an appropriate sized hole through the ceiling, using the center
point previously marked. See Figure 51. Frame the hole with
framing lumber the same size as the ceiling joists. See Figure 51.
If the area above the ceiling is NOT an attic, position and secure
the ceiling restop on the ceiling side of the previously cut and
framed hole. See Figure 52. If the area above the ceiling is an attic,
position and secure the restop on top of the previously framed
hole. See Figure 53.
NOTE: Remove insulation from the framed area in the attic before
installing the restop and/or vent pipes.
PIPESTRAP
STUDWALL
1”MIN.
(25.4mm)
FLUEOUTLET
48”
(1219mm)
FRAMING AND FINISHING
WALLFIRESTOP
HOLEIS OFF-SET
TOWARDSBOTTOM
OFWALL OPENING.

A

B

Vent Size A B
6 5/8" 10" 11"
8" 10 3/8" 12 3/8"