28 SPARC Enterprise T5140 and T5240 Servers Installation Guide • February 2008

To Verify the Operation of the Slide Rails and

the CMA
Tip – Twopeople are needed for this procedure, one to move the server in and out
of the rack, and one to observe the cables and CMA.
1. For a free-standing rack, deploy the antitilt bar.
2. Unlock the slide lock buttons (FIGURE 2-12) at the right and left sides of the
chassis.
3. Slowly pull the server out of the rack until the slide rails reach their stops.
FIGURE2-12 Unlocking the Slide Rail Assembly (Either Server)
4. Inspect any attached cables for binding or kinks.
5. Verify that the CMA extends fully and does not bind in the slide rails.
6. Verify that the server extends fully and locks in the maintenance position.
The server should stop after approximately 15 inches (40 cm) of travel.