22 SPARC Enterprise T5140 and T5240 Servers Installation Guide • February 2008
To Insert and Lock the Server in the Rack
1. Deploy the antitilt bar, if the chassis or rack is so equipped.
Caution – The weight of the servers on extended slide rails can be enough to
overturn an equipment rack.
Caution – The 2U server weighs approximately 46 lb (20.7 kg). Twopeople are
required to lift and mount the server into a rack enclosure when using the
procedures in this chapter.
2. Insert the ends of the mounting brackets into the sliding rails (FIGURE 2-7).
FIGURE2-7 Mounting the Chassis on the Slide Rails (Either Server)