23Hearth & Home Technologies • BE-36-C, BE-36-CIPI • 397-981 Rev. V 1/07
C. Vertical Penetration Framing
Installing the Ceiling Firestop
• Frame an opening 10 inches by 10
inches whenever the vent system pene-
trates a ceiling/ oor (see Figure 6.4).
• Frame the area with the same sized
lumber as used in ceiling/ oor joist.
• When installing a top vent vertical ter-
mination appliance the hole should be
directly above the appliance, unless the
ue is offset.
• Do not pack insulation around the vent.
Insulation must be kept away from the
pipe.
Figure 6.4
ATTIC ABOVE
10 IN. (254 MM)
HOLE SHOULD MEASURE
10 IN. X 10 IN.
(254 MM X 254 MM)
INSIDE TO INSIDE
10 IN.
(254 MM)
Fire Hazard
Keep loose materials or blown
insulation from touching the
vent pipe.
Installing Attic Shield
Note: An additional ceiling restop is not
required if attic shield is used.
• Frame opening for attic shield.
• Attic shield may be installed above or
below ceiling (see Figure 6.5).
• Secure with three fasteners on each
side.
• Fold tabs at top of attic shield in toward
vent pipe. Tabs must keep vent pipe
centered within shield.
• Field construct additional shield height if
insulation is deeper than height of attic
shield.
Figure 6.5 Installing the Attic Shield
National building codes recommend us-
ing attic shield to keep loose materials/
blown insulation from contacting vent.
Hearth & Home Technologies requires
the use of an attic shield.
3 FASTENERS
PER SIDE
BEND TABS IN
AROUND PIPE
ATTIC SHIELD INSTALLED
BELOW CEILING
ATTIC SHIELD INSTALLED
ABOVE CEILING
WARNING
Î