B. Sequence of Operation
1. Sequence Cycles and Shutdown
The steps in the sequence are as outlined below. When power is supplied, power switch is in the "ON" position, safety switch is engaged, and the control switch is in the "ICE" position, CB "POWER" LED turns on. The "POWER" LED indicates control voltage and will remain on unless a control voltage problem occurs. If icemaker does not start, BC actuator and proximity switch may be engaged. Move the dispense mode switch to the "CONTINUOUS" position, then dispense ice to lower the level of ice in the storage bin.
a)Fill Cycle
Reservoir is empty. LF/S and UF/S are open. WV energizes and fill cycle starts.
LF/S closes. Nothing happens at this time. Reservoir continues to fill until UF/S closes. When UF/S closes, WCR energizes, closing low water safety circuit and de‑energizing WV. GM energizes once UF/S closes.
b)Ice Purge Cycle
"GM" LED is on. GM energizes.
c)Freeze Cycle
"COMP" and "GM" LEDs are on.
#5 (DBU wire), then Comp and FM energize. Ice production starts 4 to 6 min. after Comp energizes depending on ambient and water temperature conditions. UF/S and LF/S operate WV as needed to continue the icemaking process. Refill: As ice is produced the water level in the reservoir drops. UF/S opens. Nothing happens at this time. LF/S opens. FT starts. WCR de‑energizes, energizing WV. As water fills the reservoir, LF/S closes. Nothing happens at this time. Water continues to fill and UF/S closes. FT terminates and WCR energizes, closing low water safety circuit and
d)Drain Cycle
"FLUSH" LED is on. The drain cycle occurs once every 12 hrs. for 20 min.
e)Shutdown
BC activates,
Legend: