7)Slide and remove the Compressor. Unpack the new Compressor package. Install the new Compressor.
8)Attach the Rubber Grommets of the prior Compressor.
9)Sandpaper the Suction, Discharge and Process Pipes.
10)Place the Compressor in position, and secure it using the Bolts and Washers.
11)Remove plugs from the Suction, Discharge and Process Pipes.
12)Braze the Process, Suction and Discharge lines (Do not change this order), while purging with nitrogen gas flowing at the pressure 3 - 4 PSIG.
13)Install the new Drier.
14)Check for leaks using nitrogen gas (140 PSIG) and soap bubbles.
15)See the Nameplate for the required refrigerant charge.
16)Connect the Terminals, and replace the Terminal Cover in its correct position.
17)Replace the panels in their correct positions.
18)Turn on the power supply.
35