Phase 5: Support

Draft Document for Review May 23, 2008 10:14 am

7645ProjPlan.fm

Concurrent users

Transaction processing time with database and external data sources

￿Go-Live

Plan cut-over strategy

Migration to production environment

Execute each of the above test cases introduction environment to ensure zero-performance glitch in the live environment

Training needs to be provided to all or some of the users. Recommended approach is ‘Train-the-Trainer’. Training to 3 types of users:

End Users: Functional training to the user community on how to use various functional aspects of the software. This can be done with focussed groups or general groups depending on how the client organization is structured

Role Based Training: This training is specific to certain groups. Support Purchase Administrator, Supervisor and so on, on how they can approve or disapprove certain tasks, manage their queue and so on

Administrative Training: Once the implementation team walks out, there has to be an internal designated person to manage the system. This person will be responsible for system availability, creation of new reports, enhancements, adding users, roles security groups and so on.

Phase 5: Support

Key Roles: Project Manager, Maximo Developers

Optional Roles: Business Analyst, Solution Architect

Key Activities:

Some organizations do not have strong IT presence and opt for the implementation team to provide continued system support. The basic tasks the support team has to perform are, but are not limited to:

Manage system availability

Make enhancements to accommodate evolving business processes

Create and deploy new reports

Build new integrations

Capacity planning for additional users and or organizations

The above five phase methodology is generic but includes most of the basic activities that need to be considered and planned for in an implementation. However, what the section does not include is how and what is the customer’s

Chapter 3. Project Planning