HURSPK0026/00186
Page 3 of 21
21.Slide as many large shims in the gap between the base and
The last shim may be a tight fit between the other shims and the base of the air cylinder, so that you may have to tap the shim into place.
22.Remove the stack of shims from underneath the air cylinder. If step (7) of these instructions was implemented then add two more of the thin shims (0.025" / 0.635mm) to the current stack of shims. Use this stack of shims to make three more identical shim stacks.
23.Untag the machine and raise the dome to the “up” position.
24.Add one additional 0.056" (1.4224mm) shim to each of the two sets of shims on the press bed (Refer to Step 12).
25.Lower the dome to the “down” position.
26.With the dome in the “down” position, tag and lockout the power.
27.Remove one of the four nuts and bolts from the main bell air cylinder base where it is connected to the upper
28.Slide one of the four air cylinder shim stacks from Step (22) in between the air cylinder and the upper cross member so that the shim stack lines up with the bolt hole. After the shim stack is in place, place a new longer bolt (included in the kit) through the upper cross member hole, the shims, and the air cylinder. Put the lock washer onto the bolt. Hand tighten the nut onto the bolt (See Figure 5).
29.Repeat steps (27) and (28) for the remaining three bolts of the air cylinder base.
30.Visually check if the uplock brackets are closing fully. If the brackets cannot fully close, then proceed to step (22). If the brackets can close fully then proceed to step (41).
31.When facing the main bell air cylinder from the discharge side of the press, remove the pin from the uplock bracket clevis that is connected to the
32.Loosen the “bracket clamping bolt” on the
33.Remove the spacers on the
10