VENT PIPE
SHIELD
FIGURE 17
FIRESTOP
UNDERSIDE
OF JOIST
Do not fill this space with any type of
93/4
FIGURE 16
93/4

12

INSTALLATION

WALL AND CEILING PROTECTION

HORIZONTAL VENT SECTIONS: A minimum clearance of 2” all around the vent pipe on all horizontal runs to combustibles is required. Use firestop spacer W010-1799 (supplied).

VERTICAL VENT SECTIONS: A minimum of 1” all around the vent pipe on all vertical runs to combustibles is required except for clearances in fireplace enclosures. Use firestop spacer W500-0096 (not supplied).

HORIZONTAL INSTALLATION

 

VERTICAL INSTALLATION

This application occurs when venting through an exterior wall. Having determined the correct height for the air terminal location, cut and frame a hole in the exterior wall 11 3/4“ wide by 11 3/4“ high to accommodate the firestop assembly. Dry fit the firestop assembly before proceeding to ensure the brackets on the rear surface fit within the horizontal framing.

As an alternative to framing, the vent pipe can be enclosed in the wall using Napoleon® vent sleeve VS47KT.

NOTE: THE FIRESTOP ASSEMBLY MUST BE INSTALLED WITH THE VENT SHIELD TO THE TOP.

The length of the vent shield may be cut shorter for combustible walls that are less than 8 1/2" thick but the vent shield must extend the full depth of the combustible wall.

1.Apply a bead of caulking (not supplied) around the outer edge of the inside surface of the firestop assembly, fit the firestop assembly to the hole and secure using the 4 screws W415-0026 (supplied in your manual baggie).

2.Once the vent pipe is installed in its final position, apply high temperature sealant W573-0002 (not supplied) between the pipe / liner, and the firestop.

NOTE: DO NOT FILL THE CAVITY BETWEEN THE PIPE AND THE FIRESTOP SLEEVE WITH ANY TYPE OF MATERIAL.

FIGURE 15

 

VENT

 

SHIELD

CAULKING

 

 

113/4”

FIRESTOP

113/4”

SPACER

 

DETER-

MINE

THE

CORRECT

HEIGHT

FINISHING

MATERIAL

1. Determine the air terminal location, cut and

frame 9 3/4” openings in the ceiling and the roof to provide the minimum 1“ clearance between the vent pipe and any combustible material. Try to center the vent pipe location midway between two joist to prevent having to cut them. Use a plumb bob to line up the center of the openings. material.

A vent pipe shield will prevent any materials such as insulation, from filling up the 1" air space around the pipe. Nail headers between the joist for extra support.

2.Apply a bead of caulking (not supplied) to the

framework or to the Wolf

Steel vent pipe shield plateCAULKING or equivalent (in the case of

a finished ceiling), and secure over the opening in

the ceiling. A firestop must be placed on the bottom of each framed opening in a roof or ceiling that the venting system passes through. Apply a bead of caulking (not supplied) all around and place a firestop spacer over the vent shield to restrict cold air from being drawn into the room or around the fireplace. Ensure that both spacer and shield maintain the required clearance to combustibles. Once the vent pipe is installed in its final position, apply sealant between the vent pipe and the firestop spacer.

3.In the attic, slide the vent pipe

collar down to cover up the open

VENT

end of the shield and tighten. This

PIPE

COLLAR

will prevent any materials, such as

 

insulation, from filling up the 1" air

VENT PIPE

space around the pipe.

 

SHIELD

FIGURE 18

W415-0665 / B / 02.11.08

Page 12
Image 12
Napoleon Fireplaces GD82PT-PA, GD82NT-PA manual Installation Wall and Ceiling Protection