4. Configuration
Startup Procedure for Inband Management
With inband management, the BitStorm 2600 is managed using the uplink port.
Procedure
To start up the BitStorm 2600 using inband management:
1.Specify the uplink port using the configure uplink command. It must be either eth2 (Port 2) or eth3 (Port 3). For example:
PDYN# configure uplink eth3
2.Assign an IP address, netmask, and
PDYN# configure management inband address 137.90.127.3 255.255.255.0
PDYN# configure management
Do not configure inband and
Startup Procedure for Out-of-Band Management
In
Procedure
To start up the BitStorm 2600 using
1.Assign an IP address, netmask, and
PDYN# configure management
PDYN# configure management
You can now access the web interface by typing into the Location field of your web browser the IP address assigned to the Port 1. See Using the Web Interface on page
Do not configure inband and
2.Configure routers as necessary to route data from the NOC to the BitStorm 2600.
March 2005 |