VTrak M610i, M310i, M210i Quick Start Guide

4.Slide one of the rails over the plate on one side of the subsystem. The rail is designed to slide freely over the plate.

5.Attach a flange to each end of the rail, with the rail on the opposite side of the flange from the two-hole bracket.

6.Install the rail adjustment screws (included) through the flange into the rail. There are four screws for each flange. See Figure 9.

7.Place the subsystem with mounting rails into your rack system.

8.Attach the mounting rail assemblies to the outside of the rack posts, using the attaching screws from your rack system.

9.Square the rail assemblies in the rack.

10.Tighten the adjustment screws and the attaching screws.

11.Place the VTrak subsystem onto the rails.

12.Secure the VTrak subsystem to the rack through each handle, using the attaching screws from your rack system.

Figure 8. Sliding flange installation

Rear (connector end) of the subsystem

VTrak M310i/M210i

Sliding plate

Screws (6 each side)

8

Page 8
Image 8
Promise Technology VTM310i, VTM610i, VTM210 quick start Sliding flange installation