Installing a QLogic 5800V Series switch involves the following steps:
1. Mount the Switch
2. Install the Transceivers
3. Configure the Workstation
4. Connect the Switch to AC Power
5. Connect the Workstation to the Switch
6. Configure the Switch
7. Cable Devices to the Switch
Mount the SwitchThe switch can be placed on a flat surface and stacked, or mounted in a 19”
Electronics Industries Association (EIA) rack. For weight and dimensional
specifications, refer to “Dimensions” on page A-5. Adhesive rubber feet are
provided for surface mounts. Without the rubber feet, the switch occupies 1U of
space in an EIA rack. Rack mounting requires a QLogic rail kit (part number
SB-RACKKIT).
WARNING!!
Mount switches in the rack so that the weight is distributed evenly. An
unevenly loaded rack can become unstable, possibly resulting in equipment
damage or personal injury.
AVERTISSEMENT!!
Installer les commutateurs dans l’armoire informatique de sorte que le poids
soit réparti uniformément. Une armoire informatique déséquilibré risque
d'entraîner des blessures ou d'endommager l'équipement.
WARNUNG!!
Switches so in das Rack einbauen, dass das Gewicht gleichmäßig verteilt
ist. Ein Rack mit ungleichmäßiger Gewichtsverteilung kann
schwanken/umfallen und Gerätbeschädigung oder Verletzung verursachen
¡ADVERTENCIA!
Monte los conmutadores en el estante de modo que el peso se distribuya de
manera uniforme. Un estante cuya carga no esté distribuida de manera
uniforme puede ser inestable y podría dañar el equipo o causar lesiones
personales.