Chapter 4 Common StorNext Tasks
Scheduling StorNext Events
StorNext User’s Guide 60
4Click Add. The Add Feature Schedules screen appears.
Figure 37 Add Feature
Schedules Screen
5In the Name field, enter a name for the new schedule.
6Select either Days of the Week or Days of the Month.
•If you selected Days of the Week, select the days on which you
want the event to run. To select multiple days, hold down the
CTRL key when you select subsequent days.
•If you selected Days of the Month, select the calendar dates on
which you want the event to run. To select multiple dates, hold
down the CTRL key when you select subsequent dates.
7At the Run Time field, specify the time of day you want the event to
begin.
8At the Start Window field, specify the window in which you want
the StorNext Scheduler to start the event. The Scheduler attempts to
begin the event within the specified Start Window time (e.g, 30
minutes). If the event cannot begin at that time, the Scheduler tries
again during the next cycle.