8.Other Considerations
8.1.Duty Cycle
When the NL6000 transmits data, it generates heat and the case gets warm. If the NL6000 is forced to transmit large amounts of data without a 
There are two considerations: first, limit data transmission time so that the unit will not overheat. Second, limit the duty cycle of data transmission. When operated in still air, the limits in Table 4 apply.
| Power Output | Temperature | Duty Cycle | Maximum Data Transmission | 
| 6W | 25° C | 30% | 15 Seconds | 
| 6W | 60° C | 5% | 5 Seconds | 
| 3W | 25° C | 50% | 20 Seconds | 
| 3W | 60° C | 5% | 5 Seconds | 
| 1W | 25° C | 75% | 30 Seconds | 
| 1W | 60° C | 10% | 5 Seconds | 
Table 4: Duty Cycle and Transmission Limits
The limits above can be increased significantly by placing heat sinks on the unit and/or cooling with forced air.
8.2.Troubleshooting
8.2.1.Use a Good Antenna
The antenna is the most important, but often ignored, part of the communication system. A good antenna system will increase range, increase throughput, and increase reliability. You can use directional gain antennas when operating in a 
8.2.2.Three-wire  Interface
When using a 
8.2.3.Hardware Flow Control
Many programs disable the use of hardware data flow control signals. If this is the case, the RTS/CTS flow control must be disabled. To ensure that the NL6000s internal data buffers do not overflow, you may use the XON/XOFF flow control. Refer to section 5.7.2.