Marley / MD CoolingTower / Specifications: Base
Specifications | Specification Value |
1.0Base:
28
1.1 | Furnish and install an | ■ Your specification base establishes the type, configuration, base materi- |
| al, and physical limitations of the cooling tower to be quoted. During the | |
| film fill, industrial duty, cooling tower. | planning and layout stages of your project, you will have focused your |
| Unit shall consist of _____ cell(s), as | attention on a cooling tower selection that fits your space allotment, and |
| shown on plans. The limiting overall | whose power usage is acceptable. Limitations on physical size and total |
| dimensions of the tower shall be _____ | operating horsepower avoid the introduction of unforeseen operational |
| wide, _____ long, and _____ high. Total | and |
| operating power of all fans shall not | imum fan hp/cell will work to your advantage. |
| exceed _____ kW, consisting of_____ | You are specifying a counterflow tower, which is a type |
| @ _____ kW motor(s). Tower shall be | ally |
| Marley Model _____________________. | the required thermal performance is very difficult. It effectively replaces |
|
| most makes of older |
|
| out major redesign of the existing site. |
2.0Thermal Performance:
2.1 | The tower shall be capable of cool- | ■ CTI Certification means that the cooling |
| ing _____ m3/hr of water from ____ | tower has been tested under operat- |
| °C to _____ °C at a design entering | ing conditions and found to perform as |
| air | rated by the manufacturer under those |
| The thermal performance rating shall | circumstances. It assures the buyer that |
| be Certified by the Cooling Technology | the tower is not intentionally or inadver- |
| Institute. Tower shall comply with all | tently undersized by the manufacturer. |
| ASHRAE 90.1 standards. |
|
3.0Performance Warranty:
3.1 | CTI Certification notwithstanding, the | ■ However, CTI certification alone is not sufficient to assure you that the |
| cooling tower manufacturer shall guar- | cooling tower will perform satisfactorily in your situation. Certification |
| antee that the cooling tower supplied | is established under relatively controlled conditions, and cooling towers |
| will meet the specified performance | seldom operate under such ideal circumstances. They are affected by |
| conditions when the tower is installed | nearby structures, machinery, enclosures, effluent from other sources, |
| as shown on the plans. If, because of | etc. Responsible and knowledgeable bidders will take such |
| a suspected thermal performance defi- | effects into consideration in selecting the cooling |
| ciency, the owner chooses to conduct | fier must insist by the written specification that the designer/manufac- |
| an | turer guarantee this “real world” performance. Any reluctance on the |
| under the supervision of a qualified, | part of the bidder should cause you some concern. |
| disinterested third party in accordance |
|
| with CTI, ASME or other applicable |
|
| standards during the first year of oper- |
|
| ation; and if the tower fails to perform |
|
| within the limits of test tolerance; then |
|
| the cooling tower manufacturer will |
|
| pay for the cost of the test and will |
|
| make such corrections as are appro- |
|
| priate and agreeable to the owner to |
|
| compensate for the performance defi- |
|
| ciency. |
|