Marley / MD CoolingTower / Specifications: Base
32
| Specifications |
| Specification Value |
10.0 | Access: |
|
|
10.1 | A large rectangular access door shall |
|
|
| be located in the plenum on the motor |
|
|
| side of the tower. |
|
|
11.0 | Cold Water Collection Basin: |
|
|
11.1 | The collection basin shall be heavy- |
| ■ The MD tower design offers |
| gauge galvanized steel and shall |
| may be supplied to accommodate a variety of piping schemes. Unless |
| include the number and type of suction |
| so specified, the tower you may be asked to approve may only be avail- |
| connections required to accommodate |
| able with one type of suction connection requiring you to redesign your |
| the |
| piping layout. |
| the plans. Suction connections shall be |
| The sloping floor and |
| equipped with debris screens. A fac- |
| |
| tory installed, float operated, mechani- |
| way to achieve |
| cal |
|
|
| An overflow and drain connection shall |
|
|
| be provided in each cell of the tower. |
|
|
| The basin floor shall slope toward the |
|
|
| drain to allow complete flush out of |
|
|
| debris and silt which may accumu- |
|
|
| late. Towers of more than one cell |
|
|
| shall include steel flumes for flow and |
|
|
| equalization between cells. |
|
|
13.0 | Warranty: |
|
|
13.1 | The MD cooling tower shall be free |
|
|
| from defects in materials and work- |
|
|
| manship for a period of eighteen (18) |
|
|
| months from the date of shipment. |
|
|
|
|
|
|