7.2. Assembly

STT40 / STT70

7.2. Assembly

￿Please ensure the lifting equipment has an adequate carrying capacity.

Check the load capacity where the dryer is to be installed, particularly if it is to be installed on a platform.

The place selected for installation should be as vibration-free as possible.

The main power switch must be accessible.

Ground the equipment against electrostatic charging.

)The machine must not be tilted or laid on its side.

Because of its compact construction, the dryer can be installed directly beside the processing machine (drying hopper on the processing machine) or with one or more drying hoppers as a movable facility (compact facility).

Special foundations are not necessary for installation.

The dryer must be installed on a level surface and must not be exposed to excessive humidity. The maximum permissible ambient temperature is 45 °C (113°F).

To facilitate servicing, the dryer should be installed in such a way that it is accessible from 3 sides. Make sure that the air filters can be changed without problems.

To conserve energy, keep the distance between dryer, hopper and processing machine as small as possible.

The wheels of the compact unit should be locked to ensure stable operation.

The foil skin should be removed from the drying hopper before operation.

7.3. Storage

The control system may only be stored at temperatures from 0 to +55°C (32 to +131 °F). Between delivery and machine commissioning, the equipment should be stored in a dry, dust and vibration-free room.