OPTIONAL GAS HEAT
These
TABLE 4: GAS HEAT APPLICATION DATA
All gas heaters are shipped from the factory equipped for natural gas use, but can be field converted to L.P./ Propane with Kit Model # 1NP0418. See Gas Heat Application Data Table.
0 To |
| 2,000 To | Output Capacity (Mbh) |
|
| Temp. | ||||||
|
|
|
|
| ||||||||
2,000 Feet | 4,500 Feet | 0 To | 2,000 To |
| Gas | Rise ºF | ||||||
2,000 Feet | 4,500 Feet | Available | ||||||||||
Above |
| Above | Rate |
| At | |||||||
| Above | Above | on Models |
| ||||||||
Sea Level | Sea Level | (Ft./Hr.) | Full Input | |||||||||
Sea Level | Sea Level |
| ||||||||||
|
|
|
|
|
|
|
|
|
| |||
|
|
|
|
|
|
|
|
|
|
|
| |
Max. |
| Min. | Max. | Min. | Max. | Max. |
|
| Min. |
| Max. | |
|
|
|
|
|
|
|
|
|
|
|
| |
300 |
| 150 | 270 | 135 | 240 | 213 | 15, 20 & 25 Ton | 279 | 20 |
| 50 | |
|
|
|
|
|
|
|
|
|
|
|
| |
350 |
| 175 | 320 | 160 | 280 | 241 | 25 Ton | 326 | 30 |
| 60 | |
|
|
|
|
|
|
|
|
|
|
|
|
GAS PIPING
Proper sizing of gas piping depends on the cubic feet per hour of gas flow required, specific gravity of the gas and the length of run. "National Fuel Gas Code" Z223.1 (in U.S.A.) or the current Gas Installation Codes CSA- B149.1 (in Canada) should be followed in all cases unless superseded by local codes or gas utility require- ments. Refer to the Pipe Sizing Table 5.
The heating value of the gas may differ with locality. The value should be checked with the local gas utility.
NOTE: There may be a local gas utility requirement specifying a minimum diameter for gas piping. All units require a
TABLE 5: PIPE SIZING
Length in Feet | Nominal Iron Pipe Size | ||
|
| ||
1 in. | |||
| |||
|
|
| |
10 | 520 | 1,050 | |
|
|
| |
20 | 350 | 730 | |
|
|
| |
30 | 285 | 590 | |
|
|
| |
40 | 245 | 500 | |
|
|
| |
50 | 215 | 440 | |
|
|
| |
60 | 195 | 400 | |
|
|
| |
70 | 180 | 370 | |
|
|
| |
80 | 170 | 350 | |
|
|
| |
90 | 160 | 320 | |
|
|
| |
100 | 150 | 305 | |
|
|
|
Maximum capacity of pipe in cubic feet of gas per hour. (Based upon a pressure drop of 0.3 inch water column and 0.6 specific gravity gas).
GAS CONNECTION
The gas supply line can be routed through the knock- outs located on the front of the unit or through the opening provided in the unit's base. Refer to the Dimensions and Clearances Figure 13 to locate these access openings. Typical supply piping arrangements are shown in the figures on page 15. All shaded items are
If gas supply line is routed through the unit's base ensure that the burner assembly can be removed for maintenance without disturbing the supply line. The supply piping and fittings must lie below the bottom gas manifold to avoid interference with the burner assem- bly.
Two grommets are shipped in the blower compartment (in parts bag taped to the blower housing) of every unit with gas heat and should be used in the knockouts when the gas piping penetrates the front of the unit.
After the gas supply piping has been installed, the bot- tom opening in the unit should be sealed to prevent water from leaking into the building.
Gas piping recommendations:
1.A drip leg and a ground joint union must be installed in the gas piping.
2.When required by local codes, a manual
3.Use wrought iron or steel pipe for all gas lines. Pipe compound should be applied sparingly to male threads only.
14 | Johnson Controls Unitary Products |