INTRODUCTION

This chapter contains the information you need to install youTelenetics 2185.

CUSTOMER RESPONSIBILITIES

After delivery of your equipment and before installation, you are responsible for moving it to the installation site, unpacking and check- ing it for material shortages and/or damage, which may have occurred during shipment.

SITE SELECTION AND PREPARATION

Ensure that the area where your Telenetics 2185 is to be installed is clean and free from extremes of temperature, humidity, shock, and vibration.The site must meet the physical, environmental and power requirements listed in Table 1-2 - 2185 Specifications.

Install the 2185 within 5 feet (1.5 meters) of a grounded ac outlet capa- ble of furnishing the required primary power (115 V ac or 230 V ac).The unit must also be located within 50 feet (15.2 meters) of the terminal ports and/or modems to be connected to it.At least 5 inches (12.7 cm) clearance at the rear of the unit is needed for interface cabling.