All installations and services must be performed by qualified service personnel.
B.CAD CELL CHECKOUT PROCEDURE: (OMD ONLY)
1.Remove cad cell lead wires, then start the burner. Shortly after burner starts, place a temporary jumper between terminals f & f of the oil primary control. Connect ohmmeter across cad cell lead wires - resistance should be less than 1600 ohms.
2.Stop the burner and remove temporary jumper.
3.With the burner off, check dark cell resistance across cad cell lead wires. Resistance should be greater than 20,000 ohms. If cell resistances are different from above, recheck wiring, location of cell, etc. If necessary, replace plug in portion of cell, (Part No. 350104).
4.Reconnect cad cell lead wires. Check out the oil primary control according to the instructions packed with the control.
C.HEAT EXCHANGER CLEANING INSTRUCTIONS
: The heat exchanger must be cleaned by a qualified service person.
For
For
To clean the heat exchanger,
1.First, turn off all power to the unit.
2.Remove the
3.Remove cleanout covers, the vent connector pipe to the chimney, the burner and the burner mounting plate. When removing the cleanout cover, special care must be taken not to damage the gaskets or high limit switch.
NOTE: The high limit switch may be removed for easier access to the
Should the gaskets separate, crack, break, or otherwise not be able to provide the necessary seal, the gasket must be replaced before reattaching the cleanout cover.