Site Preparation
•Complying with all local laws (codes, ordinances, and regulations) for mechanical, building, and electrical distribution systems, hazardous waste disposal, and chemical storage.
Compliance must exist prior to installation.
•Providing lifting equipment adequate to unload the system from the delivery vehicle and transport it to the site where it will be installed
•Providing someone to help lift the MSD onto the laboratory bench
•Providing adequate secure storage space for the system until it can be installed by an Agilent Technologies representative
Agilent responsibility
An Agilent Technologies service representative will install the MSD and verify its performance. The service representative’s responsibilities are limited to:
•Unpacking the MSD system and verifying that all components are present and undamaged
•Connecting the carrier gas line to the instrument from the tank, regulators, and lines previously installed by the customer
•Installing, connecting, and turning on MSD system components
•Verifying that the system meets Agilent Technologies performance standards
•Providing basic user familiarization for system hardware and software
•Signing the customer up through the Response Centers for instrument and software support
Site Preparation Guide | 17 |