Chapter 2 System Installation
2.1.3 Installation and Commissioning Checklist
•Insulated Phillips and flathead screwdriver sets
•Insulated wire & cable strippers/crimpers (for ground lug, DC cable, alarm, and GMT cable installations)
•8mm socket or wrench for ground cable installation
1
2.1.3Installation and Commissioning Checklist
•AC/DC system shelf mounted securely in rack
•1 RU Distribution Shelf mounted securely in rack directly above the system shelf (if applicable)
•AC and DC cabling meets local and national electrical code specifications
•Installation in ETSI racks allows for
•System alarm cabling is installed and secure
•Power cables are secure and installed correctly
•Rectifiers are installed and seated correctly in the system shelf
•The controller and 1 RU Distribution faceplates are installed and secure (if applicable)
•System shelf rear cover is installed and secured
•System powers up and all red LEDs are extinguished after a few minutes
2.1.4Installation Materials
Table
Table | Supplied Materials for the System Shelf | ||
|
|
|
|
Description |
| Qty | Use |
|
|
| |
M6 0x20mm screw (thread forming) | 6 | Shelf mounting screws (ETSI racks/cabinets) | |
|
|
| |
6 | Shelf mounting screws (ANSI, IEC racks/ | ||
|
|
| cabinets) |
|
|
|
|
M6 cage nut |
| 6 | Shelf mounting nut (ETSI racks/cabinets) |
|
|
| |
Mounting bracket 600mm ETSI rack | 2 | Ear mounts (ETSI racks/cabinets) | |
|
|
|
|
2A GMT fuse |
| 2 | GMT fuse panel |
|
|
|
|
5A GMT fuse |
| 2 | GMT fuse panel |
|
|
|
|
10A GMT fuse |
| 2 | GMT fuse panel |
|
|
|
|
15A GMT fuse |
| 2 | GMT fuse panel |
|
|
| |
Standard AC plug | 4 | AC plugs that meet local requirements | |
|
|
|
|
Cable ties |
| 12 | Securing cables |
|
|
|
|
ESD wrist strap |
| 1 | ESD protection |
|
|
|
|
Cisco AC/DC Power System User Guide, R1.0
May 2006 |