Installation Prerequisites

Guidelines for Interface Processor Installation and Removal

This section describes mechanical functions of system components, emphasizes the importance of following correct procedures to avoid unnecessary board failures, and is for background only; specific procedures follow in the section “FEIP Installation” on page 21.

You can remove and replace interface processors while the system is operating; you do not need to notify the software or reset the system power. This functionality enables you to add, remove, or replace interface processors with the system online, which provides a method that is seamless to end users on the network, maintains all routing information, and ensures session preservation.

After an interface processor is reinstalled, the system brings on line only interfaces that match the current configuration and were previously configured as up; all others require that you configure them with the configure command.

Caution The system can indicate a hardware failure if you do not follow proper procedures. Remove or insert only one interface processor at a time. Allow at least 15 seconds for the system to complete the preceding tasks before removing or inserting another interface processor. Disrupting the sequence before the system completes its verification can cause the system to interpret hardware failures.

Cisco 7000 series and Cisco 7500 series routers have ejector levers located on the ends of the interface processor slots. (See Figure 1a.) The function of the ejector levers is to align and seat the interface processor connectors in the backplane. Failure to use the ejector levers and insert the interface processor properly can disrupt the order in which connector pins make contact with the backplane.

Follow the FEIP installation and removal instructions carefully, and review the following examples of incorrect insertion practices and their results:

Using the handle to force the interface processor all the way into the slot can pop the ejector levers out of their springs. If you then try to use the ejector levers to seat the interface processor, the first layer of pins (which are already mated to the card or interface processor) can disconnect and then remate with the backplane, which the system interprets as a board failure.

Using the handle to force or slam the interface processor all the way into the slot can damage the pins on the board connectors if they are not aligned properly with the backplane.

When using the handle (rather than the ejector levers) to seat the interface processor in the backplane, you might need to pull the interface processor back out and push it in again to align it properly. Even if the backplane pins are not damaged, the pins mating with and disconnecting from the card or interface processor might cause the system to interpret a board failure. Using the ejector levers ensures that the board connector mates with the backplane in one continuous movement.

Using the handle to insert or remove an interface processor, or failing to push the ejector levers fully against the interface processor, can leave some (not all) of the connector pins mated to the card or interface processor, a state which hangs the system. Using the ejector levers and making sure that they are pushed fully into position ensures that all three layers of pins are mated with (or free from) the backplane.

Use the ejector levers when removing an interface processor to ensure that the backplane connector pins disconnect from the interface processor in the sequence expected by the system. Any interface processor that is only partially connected to the backplane can hang the bus. Steps for correctly performing OIR are included with the following procedures for installing and removing the FEIP.

6Fast Ethernet Interface Processor (FEIP) Installation and Configuration

Image 6
Contents Corporate Headquarters Document Contents If You Need More InformationInstallation Prerequisites Installation PrerequisitesSoftware and Hardware Prerequisites Safety Guidelines List of Parts and ToolsElectrical Equipment Guidelines Telephone Wiring Guidelines Safety GuidelinesPreventing Electrostatic Discharge Damage Guidelines for Interface Processor Installation and Removal Guidelines for Interface Processor Installation and Removal Orientation ShownMicrocode Overview Fast Ethernet OverviewIeee 802.3u 100BaseT Specifications Ieee 802.3u 100BaseT Specifications100BASE-FX Multimode 100BASE-FX Single Mode ParameterWhat Is the Cisco 7000 Series? DTE DTEWhat Is the Cisco 7000 Series? Cisco 7000 Interface Processor EndWhat Is the Cisco 7500 Series? Cisco 7505 Interface Processor EndWhat Is the Cisco 7500 Series? Cisco 7507 Interface Processor EndCisco 7513 Interface Processor End What Is the FEIP? What Is the FEIP?Fast Ethernet Interface Processor FEIP-2TX Feip LEDs LEDs on an Feip Port Adapter Partial Faceplate View1FE-TX Port Adapter Faceplate View Feip Receptacles, Cables, and PinoutsFeip Receptacles, Cables, and Pinouts 1FE-FX Port Adapter Faceplate ViewRJ-45 Connector Pinout Pin Description1FE-FX Duplex SC Connector MII Connector Pinout Pin Out In/Out DescriptionFeip Installation Feip InstallationRemoving an Feip Installing an Feip Installing an FeipAttaching Fast Ethernet Interface Cables Attaching Fast Ethernet Interface Cables Attaching the Ferrite Bead around the RJ-45 Cable Using LEDs to Check Feip Status Using LEDs to Check Feip StatusConfiguring the Fast Ethernet Interfaces Configuring the Fast Ethernet InterfacesSlot Interface Routerconfig-int#ip address 1.1.1.10 Router# configure terminalRouterconfig# interface fa 1/0/0 Router# copy running-config startup-configConfiguring Interfaces-Descriptions and Examples Routerconfig# interface fastethernet 3/0/0Router# sh int fa 3/0/0 Using show Commands to Verify the Feip Status Checking the ConfigurationStep Router# sh int fastethernet 2/0/0 Using show Commands to Display Interface InformationChecking the Configuration Router# show interfaces fastethernet 2/0/0Router# show controllers cbus System image file is biff/rsp-jv-mz, booted via tftp from Router# show versionRouter# show diag Slot database informationUsing the ping Command to Verify Network Connectivity Upgrading Feip MicrocodeUpgrading Feip Microcode Router# show flash Router# copy tftpvip11-1 slot0vip11-1Routerconfig# microcode vip2 flash slot0vip11-1 To exit configuration mode, press Ctrl-ZDocumentation CD-ROM Obtaining DocumentationWorld Wide Web Ordering DocumentationCisco.com Contacting TAC by Using the Cisco TAC WebsiteObtaining Technical Assistance Technical Assistance CenterObtaining Technical Assistance