7.3Preferred Grounding Configuration with Power-Tie Switchgear
Figure 5 Preferred Grounding Configuration, Power-Tie Systems
Multi-Module Systems can be used with Power-Tie switchgear to provide dual critical load busses. The Power-Tie switchgear permits transferring critical loads from one critical bus to the other so that one UPS system and associated breakers can be de-energized for maintenance. Certain con- figurations of Power-Tie equipment also permit the operator to continuously parallel the output of both UPS systems.
In tied systems, each SCC must have its neutral solidly connected to the Power-Tie switchgear neutral. The UPS modules, as usual, must have their output neutrals solidly connected to their respective SCC neutrals. There should not be a connection between the service entrance neutral and either the SCC or module neutrals.
NOTE
It is essential to run a neutral connection between the tie switchgear and both SCCs as shown in the illustration above.
Configuring Your Neutral and Ground Connections | 17 |