Magnum | Installation and User Guide 03/06) |
so the user may elect to Ground either + or = terminal to suit the customer’s use. Before connecting hot lines to the Terminal Block of
125VDC, always use a digital voltmeter to measure the output voltage of the power supply and determine the lead which is more “+ve potential”. The more “+ve” voltage lead from 48V or
B4.1 UL Requirements for DC-powered units
1.Minimum 18AWG cable for connection to a Centralized DC power source.
2.Minimum 14AWG cable for connection to a earthing wiring.
3.Use only with Listed 10 A circuit breaker provided in building installation.
4.“Complies with FDA radiation performance standards, 21 CFR subchapter J.” or equivalent.
5.Fastening torque of the lugs on the terminal block: 9
6.Centralized DC Power Source cable securement, use at least four cable ties to secure the cable to the rac,k at least 4 inches apart, with the first one located within 6 inches of the terminal block.
B5.0 OPERATION
Operation of Magnum
Similarly to order the optional 24VDC or 125VDC industrial specific power supply factory installed, add a suffix of “24VDC” or “125VDC” after the product ‘s standard model #. Example: Magnum
B7.0 TROUBLESHOOTING
Please refer to Section 6.0 for troubleshooting
APPENDIX C: Internal DC
C1.0 SPECIFICATIONS - FOR MAGNUM 6K8-SERIES FIBER SWITCH
Power Supply (Internal,
DC Power Connector: First Source: “A+”,
GND: Terminal for “earth” or ground wire connection to the hub chassis
Input: Two separate sources, each at 36 - 70 VDC
Power Supply (Internal, 24VDC
DC Power Connector: First Source: “A+”,
GND: Terminal for “earth” or ground wire connection to the hub chassis
Input: Two separate sources, each at 18 - 36 VDC
www . GarrettCom . com