6. ACCEPTANCE TESTS
6.9. FUNCTIONS
6.9.1 50BF 1P UNIT TEST
1.Change setpoint GENERAL/FUNCTION PERMIT/50BF 1P FUNCTION to PER.
2.Change setpoint GENERAL/FUNCTION PERMIT/50BF 3P FUNCTION to NO PER.
3.Change setpoint TABLE 1/FUNCTION PERMIT/3P No INT FUNCT to NO PER.
4.Change setpoint 50BF SETTINGS/Nº OUTPUT STAGES to 2.
5.The precision timer will be started at the same time than the corresponding contact converter (digital input) is energized. The timer stop input will be wired to any DBF contact under test, i.e. contact
6.Apply 2A to terminals
7.Energize digital input CC1 PHASE A BF INITIATE (terminal
8.Check that after T1 time delay (1s), the following contacts are closed:
In case the relay under test includes an expansion board, check also the operation of the following contacts:
9.Check that after 2nd Stage Timer delay (2s), the following contacts are closed:
and if the relay is equipped with an expansion board also the following contacts must be closed:
10.Repeat steps 7, 8, 9 and 10 using phase B current
11.Repeat steps 7, 8, 9 and 10 using phase C current
12.Change setpoint TABLE 1/50BF SETTINGS/Nº OUTPUT STAGES to 1.
13.Repeat steps 7 to 12 to check that in this case contacts
DBF Breaker Failure Protection | 33 |