·The direct PV generator voltage is availa- ble internally after connecting the PV generator to the solar inverter via the DC connectors and switching on the PV generator switch!

·Please note that the input capacitors are still charged even after switching off the PV generator switch or removing the PV generator plug connection!

·After disconnecting the AC and DC side, the solar inverter still conducts voltage for up to ca. five minutes!

·Therefore, wait for at least five minutes until the internal voltage has dissipated. Then you can work on the terminals!

Please note the general safety informa- tion on pages 83 and 84!

98

Image 22
Contents Manual Solar Inverters NT 2600, NT 4000180 mm 300 mm 510 mm List of Contents General information Information on installationCommissioning Information on operationAppendix General information General safety information Opening the unit Inspecting the delivery Scope of supplyPage Standard components of the PV system PV generator switchStandard components of a PV system SensorEN Mains fuse Energy meterProtection concept Information on installation Mechanical safety Information on cleaning Warm Air 300 mm 150 mm Cool · Thermal interaction · Protection from damp and foreign bodiesElectrical connection and cable entry Fig. Inlets on the unit undersideThree-phase grid connection distributed over three units Grid connectionPage PV generator connection · Preparation · ConnectionImportant information Page Communication connections · Connection Connecting the sensors · Optional irradiation sensor Page Switching the solar inverter on and off · Switching on · Switching off Configurations Plus Minus ESC/CUR UP/DWN Structure and menu levels for configuration SaveLanguage LCD Contrast Software Information on operation Display LineData memory Sunways NT Monitor software Initialising the remote modem Connection and circuitry options Connection to PC via RSIndividual PV system with modem for remote inquiry Connection to modem via RSConnection to PC via RS 485/RS Stripped length 11 mm Jumper JP400 see aboveInverter to299 Connection to modem via RS 485/RS Cable type B Connector To modem Pole Signal cables Configuring the interface cablesPole Signal cables Cable type a FemaleConverter Cable type C Connector To modem PoleLocating jumper JP400 in the Sunways Solar Inverter · Monthly values · Fault dataSunways NT Monitor data acquisition · Online values · 15 minute valuesOperation of Sunways NT Monitor · Setting menu· Data menu · Help menu Line Error UAC1 Overvoltage Line Error UAC3 OvervoltageLine Error UAC3 Undervoltage Line Error UAC1 UndervoltageLine Error AFI Residual current Line Error UDC OvervoltageLine Error Temp Overtemperature Fault diagnosis Fault display Causes UDCFault display Causes UAC3AFI · Warranty period · Conditions· Exclusion of liability Appendix Subject and abbreviation index Designation DescriptionDesignation · Differential measurement Functional principle and explanations· DC and AC filters · Solar inverter with Heric technology· RS 485 and RS 232 interfaces · Microcontroller· LCD display · Sensor interface· MPP control Block diagram PV-GENERATORAFI Technical data Model Solar Inverter NTSolar Inverter NT Page Page Page Page 146 147 148 149 General exclusion of liability Registered trademarksPage Sunways AG Photovoltaic Technology Macairestraße 3