Output terminal block
Earthing wires

2. Installation

2.6 Connection to the connection modules

This type of connection must be carried out by qualified electrical personnel.

Before carrying out any connections, check that the battery circuit breaker 2 is OFF and that the upstream protection devices ( AC-power source) are open (OFF).

29

28

The overall cable diameter and the cross-sectional area of the three wires depends on the UPS rating.

 

Comet EXtreme

Comet EXtreme

 

4,5 to 6 kVA

9 to 12 kVA

 

 

 

Cable diameter

15 to 25.5 mm

15 to 25.5 mm

 

 

 

Cross-sectional area of each wire

 

 

Flexible wire

4 to 10 mm2

10 mm2

Rigid wire

4 to 16 mm2

10 to 16 mm2

 

 

 

Recommended upstream circuit

 

 

breaker

 

 

Nominal rating

C60N 32A 2P

C60N 63A 2P

(47 to 63Hz, 230V)

(maximum line

(maximum line

 

current = 26A)

current = 52A)

Maximum rating

C60N 40A 2P

C60N 80A 2P

(47 to 63Hz, 187V)

(maximum line

(maximum line

 

current = 32A)

current = 64A)

 

 

 

1.Remove the terminal-block cover 28 .

2.Remove the cable entry knockouts from the cover.

3.Loosen the cable clamp 29 .

94. Insert the cable supplying the equipment and the power cable

10through the terminal-block cover 28.

28

Always connect the earthing wire first.

Input terminal

10 block

9

29

5. Connect the three wires of the equipment cable to the output terminal block 9 .

6.Connect the three wires of the power cable to the input terminal block 10 .

7.Tighten the cable clamp 29 .

8.Refit and secure the terminal-block cover 28 .

51033212EN/AC - Page 17

Image 17
Contents Comet EXtreme InstallationIntroduction Pictograms Using this documentForeword Contents Glossary Index Failure of AC input power and operation on battery powerComet EXtreme range Presentation6 kVA tower models 6 kVA rack models12 kVA tower models 12 kVA rack models Comet EXtreme 9 and 12 kVA BackComet EXtreme 4.5 and 6 kVA Battery extensions for UPS backup times of 80 minutes EPO Emergency Power OffBattery extensions for 4.5 or 6 kVA Comet EXtreme OptionsCLA Battery extensions for 9 or 12 kVA Comet EXtremeControl panel Alarms Battery Load RemainingUnpacking and checks InstallationElectronic module Battery module Electronic module Rack mounting diagram with rails Installation of the rack versionCheck that the battery circuit breaker 2 is OFF Battery-module connectionsConnection to the RS 232 communications port optional Installation of the communications-card optionConnection to the connection modules Always connect the earthing wire firstOperation ON-LINE operating modeBargraph indications When button 15 is pressedStart-up Failure of AC input power and operation on battery power Personalization Personalizable function Default settingFunction On / OFF conditions tabPersonalizable function Default setting Options Battery tabOutput tab By-pass tabShutdown Connected equipment is no longer supplied with powerTroubleshooting MaintenanceFrench Training Center on Montbonnot site USA Training Center on Costa Mesa siteMaintenance Disconnecting the connection module Replacement of the electronic moduleConnected equipment is again protected by the UPS Reconnecting the connection moduleEnvironment UPS recycling at the end of service lifeThis product has been designed to respect the environment PackingAppendices ON-LINE modeGlossary Manual bypassStart on battery power Sleep modeTolerance for AC-power Out of toleranceUPS Driver Index32 51033212EN/AC