Preparing for Component Installation

Step 1 Check the color of the Power Status LED (see the “Front Panel LEDs” section on page 3-2).

Green indicates that the server is in main power mode and must be shut down before it can be safely powered off. Go to Step 2.

Amber indicates that the server is already in standby mode and can be safely powered off. Go to Step 3.

Step 2 Invoke either a graceful shutdown or a hard shutdown:

Caution To avoid data loss or damage to your operating system, you should always invoke a graceful shutdown of the operating system.

Graceful shutdown—Press and release the Power button. The operating system will perform a graceful shutdown and the server goes to standby mode, which is indicated by an amber Power Status LED.

Emergency shutdown—Press and hold the Power button for 4 seconds to force the main power off and immediately enter standby mode.

Step 3 Disconnect the power cords from the power supplies in your server to completely power off the server.

Removing and Replacing the Server in a Rack

To remove or replace the server in a rack, follow these steps:

Tip You do not have to remove the server from the rack if you can slide it forward enough to remove the top cover and safely view and access the internal components. Always disconnect all power cords before removing the top cover.

Step 1 Remove a server from a rack:

a.Disconnect all cables from the server. You can leave the cables routed through the CMA.

a.Loosen the two captive thumbscrews that secure the front of the server to each rack post.

b.Pull the server out of the front of the rack until the slide rails stop against the internal lock.

c.Press the removal release clip on each slide rail (see Figure 2-4 on page 2-7), and then continue pulling the server out evenly until it clears the slide rails.

Step 2 Replace a server in a rack:

a.Align the mounting brackets that are attached to the server sides with the front of the empty slide rails.

b.Push the server into the slide rails until they stop against the internal stops.

c.Press the installation release clip on each slide rail (see Figure 2-4 on page 2-7), and then continue pushing the server in evenly until its front flanges touch the rack posts.

d.Tighten the thumbscrews on each flange to secure the server to the rack posts.

Cisco UCS C200 Server Installation and Service Guide

3-8

OL-20732-02

 

 

Image 48
Contents Cisco UCS C200 Server Installation and Service Guide Page N T E N T S Status LEDs AC Power Cord Illustrations OL-20732-02 Related Documentation AudienceOrganization Conventions Bewaar Deze InstructiesConservez CES Informations Guarde Estas Instrucciones GEM Disse Anvisninger Xii Obtaining Documentation and Submitting a Service Request Xiv Overview Optional DVD module Rear Panel Features Feature or Component Cisco UCS C200 Server LFF RAID = redundant array of independent disks Installing the Server Shipping Box Contents Unpacking and Inspecting the ServerPreparing for Installation Installation GuidelinesSlide Rail Adjustment Range Rack RequirementsRequired Equipment Installing the Server Into a Rack Attaching a Slide-Rail Assembly Attaching Mounting Brackets to the Server Attaching the Cable Management Arm Initial Server Setup Connecting and Powering On the Server Standalone ModeOL-20732-02 Cisco UCS C200 Server Installation and Service Guide NIC Modes and NIC Redundancy Settings System Bios and Cimc Firmware Updating the Bios and Cimc FirmwareAccessing the System Bios Service Jumper Locations Motherboard JumpersUsing the Bios Recovery Jumper J1E5 to Recover Corrupt Bios Clearing the Cimc Admin Password Using Jumper J45 Using the Clear Cmos Jumper J1E6 Clearing the Bios Admin Password Using Jumper J1E4 OL-20732-02 Server Configuration Utility Server Monitoring and Management ToolsCisco Integrated Management Interface Cimc Status LEDs Front Panel LEDsLED Name State CPU fault Off-All CPUs are operating properly Rear Panel LEDsLED Name State LED Name State Preparing for Component Installation Shutting Down and Powering Off the ServerRemoving and Replacing the Server in a Rack Removing and Replacing the Server Top Cover Removing the Top Cover of the ServerRemoving the Front Cover of the Server Replaceable Component Locations 6shows the Large Form Factor LFF version of the serverReplaceable Component Locations, Small Form Factor Top View Installing or Replacing Components Maintaining the Server Installing or Replacing Components 282338 Alternate Front Panel Module Cable Routing Installing Hard Drives or Solid State Drives HDD01 HDD02 HDD03 HDD04 HDD01 HDD02 HDD03 HDD04 HDD05 HDD06 HDD07 HDD08 Installing Power Supplies PSU2 PSU1Installing a Fan Tray 15 Removing and Replacing a Fan Tray Installing DIMMs Memory Performance Guidelines and Population RulesMemory Population Rules Low-Voltage Dimm Considerations Generation M2 Only Dimm Installation Procedure 17 Removing and Replacing Memory Modules Installing CPUs and Heatsinks 18 Removing and Replacing CPUs and Heatsinks Installing a Motherboard Cmos Battery Installing a Trusted Platform Module 19 Removing and Replacing a Motherboard Cmos BatteryTPM Replacing a PCIe Riser Card Assembly 21 Removing and Replacing a PCIe Riser Card Assembly Replacing a PCIe CardReplacement Procedure PCIe Slot How to Identify Which Power Supply Model is in Your Server Resolving Insufficient Memory Space to Execute Option ROMs Resolving Insufficient 16-Bit I/O Space Replacing an LSI MegaRAID Battery Backup Unit Replacing an LSIiBBU06 BBU24 Removing and Replacing an LSIiBBU06 BBU Replacing an LSIiBBU08 BBU 25 Replacing a Mounting Bracket for the LSIiBBU08 BBUScrews 27 Removing and Replacing an LSIiBBU06 BBU Installing a Mezzanine Card Mezzanine card retaining posts three Technical Specifications Physical SpecificationsEnvironmental Specifications Power SpecificationsCable and Power Cord Specifications KVM CableSupported Power Cords and Plugs Description Feet Meters IllustrationAC Power Cord Illustrations This section contains the AC power cord illustrationsCAB-9K10A-EU CAB-9K10A-SW CAB-N5K6A-NA CAB-9K12A-NA OL-20732-02 RAID Controller Considerations Supported RAID Controllers and Required CablesR200-SASCBL3 Enabling the Mezzanine Card RAID Controller in the Bios RAID Controller CablingHow to Determine Which Controller Is in Your Server Cisco UCS C200 LFF Server CablingCisco UCS C200 SFF Server Cabling How To Launch Option ROM-Based Controller Utilities From your For More Information OL-20732-02 Installation for Cisco UCS Integration OL-20732-02