Replacing a Front Panel Control Module or DVD Module (Small Form Factor Only)

The Small Form Factor version of the server (PID UCSC-BSE-SFF-C200) can contain a replaceable front panel control module or an optional DVD module in its place. This section describes how to replace a front panel control module or a DVD module.

The qualified and supported part numbers for this component are subject to change over time. For the most up-to-date list of replaceable components, see the following URL and then scroll to Technical Specifications:

http://www.cisco.com/en/US/products/ps10493/products_data_sheets_list.html

To replace or install a front panel control module or DVD module, follow these steps:

Step 1 Remove a module (see Figure 3-8):

a.Power off the server as described in the “Shutting Down and Powering Off the Server” section on page 3-7.

b.Disconnect all power cords from the power supplies.

c.Slide the server out the front of the rack far enough so that you can remove the top cover and front cover. You might have to detach cables from the rear panel to provide clearance.

Caution If you cannot safely view and access the component, remove the server from the rack.

d.Remove the top cover as described in the “Removing and Replacing the Server Top Cover” section on page 3-9.

e.Remove the front cover as described in the “Removing and Replacing the Server Front Cover (Small Form Factor Only)” section on page 10.

f.Disconnect the two cable harnesses from the connectors on the module.

g.Remove the single retaining screw that secures the module to the chassis.

h.Slide the module toward the server front about 0.25-inches (6 mm) until the three keyed holes in the bottom of the module free from the three pegs on the chassis.

i.Lift the module straight up and out of the chassis.

Step 2 Replace a module (see Figure 3-8and Figure 3-9):

a.Set the new module in the chassis, aligning the three keyed holes in the bottom of the module with the three pegs on the chassis.

b.Slide the module toward the chassis rear about 0.25-inches (6 mm), until the three keyed holes lock onto the three chassis pegs.

c.Install the single retaining screw that secures the module to the chassis.

d.Reconnect the two cable harnesses to the connectors on the module.

Note The cabling connections and routing differ for the two types of modules. If you are replacing one type of module with another, you must replace the cables and their connection to the motherboard. See Figure 3-9.

e.Replace the front cover as described in the “Removing and Replacing the Server Front Cover (Small Form Factor Only)” section on page 10.

 

Cisco UCS C200 Server Installation and Service Guide

3-14

OL-20732-02

Image 54
Contents Cisco UCS C200 Server Installation and Service Guide Page N T E N T S Status LEDs AC Power Cord Illustrations OL-20732-02 Related Documentation AudienceOrganization Conventions Bewaar Deze InstructiesConservez CES Informations Guarde Estas Instrucciones GEM Disse Anvisninger Xii Obtaining Documentation and Submitting a Service Request Xiv Overview Optional DVD module Rear Panel Features Feature or Component Cisco UCS C200 Server LFF RAID = redundant array of independent disks Installing the Server Shipping Box Contents Unpacking and Inspecting the ServerPreparing for Installation Installation GuidelinesSlide Rail Adjustment Range Rack RequirementsRequired Equipment Installing the Server Into a Rack Attaching a Slide-Rail Assembly Attaching Mounting Brackets to the Server Attaching the Cable Management Arm Initial Server Setup Connecting and Powering On the Server Standalone ModeOL-20732-02 Cisco UCS C200 Server Installation and Service Guide NIC Modes and NIC Redundancy Settings System Bios and Cimc Firmware Updating the Bios and Cimc FirmwareAccessing the System Bios Service Jumper Locations Motherboard JumpersUsing the Bios Recovery Jumper J1E5 to Recover Corrupt Bios Clearing the Cimc Admin Password Using Jumper J45 Using the Clear Cmos Jumper J1E6 Clearing the Bios Admin Password Using Jumper J1E4 OL-20732-02 Server Configuration Utility Server Monitoring and Management ToolsCisco Integrated Management Interface Cimc Status LEDs Front Panel LEDsLED Name State CPU fault Off-All CPUs are operating properly Rear Panel LEDsLED Name State LED Name State Preparing for Component Installation Shutting Down and Powering Off the ServerRemoving and Replacing the Server in a Rack Removing and Replacing the Server Top Cover Removing the Top Cover of the ServerRemoving the Front Cover of the Server Replaceable Component Locations 6shows the Large Form Factor LFF version of the serverReplaceable Component Locations, Small Form Factor Top View Installing or Replacing Components Maintaining the Server Installing or Replacing Components 282338 Alternate Front Panel Module Cable Routing Installing Hard Drives or Solid State Drives HDD01 HDD02 HDD03 HDD04 HDD01 HDD02 HDD03 HDD04 HDD05 HDD06 HDD07 HDD08 Installing Power Supplies PSU2 PSU1Installing a Fan Tray 15 Removing and Replacing a Fan Tray Installing DIMMs Memory Performance Guidelines and Population RulesMemory Population Rules Low-Voltage Dimm Considerations Generation M2 Only Dimm Installation Procedure 17 Removing and Replacing Memory Modules Installing CPUs and Heatsinks 18 Removing and Replacing CPUs and Heatsinks Installing a Motherboard Cmos Battery Installing a Trusted Platform Module 19 Removing and Replacing a Motherboard Cmos BatteryTPM Replacing a PCIe Riser Card Assembly 21 Removing and Replacing a PCIe Riser Card Assembly Replacing a PCIe CardReplacement Procedure PCIe Slot How to Identify Which Power Supply Model is in Your Server Resolving Insufficient Memory Space to Execute Option ROMs Resolving Insufficient 16-Bit I/O Space Replacing an LSI MegaRAID Battery Backup Unit Replacing an LSIiBBU06 BBU24 Removing and Replacing an LSIiBBU06 BBU Replacing an LSIiBBU08 BBU 25 Replacing a Mounting Bracket for the LSIiBBU08 BBUScrews 27 Removing and Replacing an LSIiBBU06 BBU Installing a Mezzanine Card Mezzanine card retaining posts three Technical Specifications Physical SpecificationsEnvironmental Specifications Power SpecificationsCable and Power Cord Specifications KVM CableSupported Power Cords and Plugs Description Feet Meters IllustrationAC Power Cord Illustrations This section contains the AC power cord illustrationsCAB-9K10A-EU CAB-9K10A-SW CAB-N5K6A-NA CAB-9K12A-NA OL-20732-02 RAID Controller Considerations Supported RAID Controllers and Required CablesR200-SASCBL3 Enabling the Mezzanine Card RAID Controller in the Bios RAID Controller CablingHow to Determine Which Controller Is in Your Server Cisco UCS C200 LFF Server CablingCisco UCS C200 SFF Server Cabling How To Launch Option ROM-Based Controller Utilities From your For More Information OL-20732-02 Installation for Cisco UCS Integration OL-20732-02