Site Preparation

Figure 5 Condenser planning dimensional data—Six- and eight-fan units

131-1/2"

87-1/8"

(2213mm)

(3340mm)

37-7/8"

(962mm)

 

59"

 

(1499mm) 18"

 

(457mm)

 

124"

86-3/4"

(3150mm)

87-1/8"

(2213mm)

171-1/2"

(4356mm)

37-7/8"

(962mm)

18"

(457mm) 70" (1778mm)

(2203mm)

Overalll height to the top

of the fan guard is 43-1/8” (1095mm).

1-1/2" (38mm) diameter hole for rigging

(typ.4)

86-3/4"

(2203mm)

164"

(4166mm)

Liebert recommends a clearance of 36" (915mm) on each side for proper

42"

ANCHOR PLAN

122" (3099 mm)

operation and component access.

Electric

Box

End

(1067mm)

Legs supplied with

Six-Fan

 

 

See Figure 6 for typical

84-3/4"

Lee-Temp option only

Condenser

(2153mm)

condenser footprint dimensions.

 

 

 

 

 

 

 

 

82" (2083 mm)

 

 

ANCHOR PLAN

 

42"

 

 

 

 

80" (2032 mm)

 

 

 

 

 

(1067mm)

Electric

Legs supplied with

Eight-Fan

 

Box

84-3/4"

Lee-Temp option only

Condenser

End

(2153 mm)

7

Image 11
Contents Liebert Air Cooled, Direct Drive Condensers Fan Speed Control 2-8 fan models only Three-phase voltage is only voltage available as standardExample DCDF165-Y On condensers with VFD Control, Lee-temp receivers,Table of Contents Operation System MaintenanceVariable Frequency Drive Product Description and FeaturesHead Pressure Control Types Fan SpeedTransient Voltage Surge Suppression Option Typical System ConfigurationsSound Level Options Lee-Temp Discharge Fan Speed and VFD Site Considerations Dimensions and Weights1067 mm See for typical condenser footprint dimensionsFour-Fan41-3/16 Condenser 1046mm See for typical Operation and component accessCondenser footprint dimensions Typical condenser footprint-dimensions Piping connections for 6- and 8-fan Fan Speed Condensers Site Preparation Quiet-Line Models Condenser physical dataQuiet-Line Condenser Models Refrigerant Planning ValuesR-407C refrigerant required, approximate ReceiverPacking Material Equipment InspectionUnpacking the Unit Handling Unit on the SkidRemoving the Skid and Attaching Slings Step Attaching legs to a 6-fan or 8-fan unitAttaching sling to a 6-fan or 8-fan unit for moving Mounting the CondenserElectrical Supply Preparation Line Voltage Wiring50Hz condenser full load amp values 60Hz condenser dataLee-Temp receiver electrical data, 50Hz and 60Hz Low Voltage Control WiringLow Voltage Monitoring Wiring-TCDV Only Electrical ConnectionsVFD Control Condensers Tcdv only Wye-Connected Power SupplyDelta-Connected Power Supply Disconnect EMC Filter for Delta-Connected Power Electrical Field Connection Descriptions Electric service connection and fuse blockElectrical field connections for VFD control condensers Inspection and Installation Piping Guidelines Refrigeration Piping ConnectionsVFD and Fan Speed Control condenser piping Field Piping InstallationLee-Temp head pressure control condenser piping General arrangement-Air cooled models with Lee-Temp control Single Circuit ShownSystem Dehydration/Leak Test and Charging Procedures Other Moving and Placing EquipmentElectrical PipingStartup Startup ChecklistSystem Maintenance General ProceduresHow to Clean Special ProceduresCondenser Cleaning When to CleanFan Motors Maintenance Inspection ChecklistMonthly Semiannually Condenser Condenser Electrical Panel Condenser Electric PanelSymptom Possible Cause Check or Remedy TroubleshootingSystem Maintenance System Maintenance Page That Ne tIti Ti n