Liebert 205 251, 104 165, 308 415, 1010, 510 616 830 manual Removing the Skid and Attaching Slings

Page 19

Inspection and Installation

3.4Preparing a 1-, 2-, 3- or 4-Fan Condenser for Moving and Installation

3.4.1Removing the Skid and Attaching Slings

1.Install the legs, provided by Liebert, on the condenser with the mounting bolts, also provided by Liebert. Liebert recommends using a 5/8" socket and ratchet.

2.Place slings or equivalent items through holes in the legs on 1, 2- and 3-fan condensers (see Step 2 and Step 3 in Figure 13). Use eyebolts for attaching a sling or similar equipment to 4-fan units.

3.Using spreader bars and a crane, or similar lifting equipment, lift the condenser off the skid to allow safely turning the condenser upright.

4.Lift the condenser and move it to the installation location.

Figure 13 Attaching legs and sling to a 1-, 2-, 3- or 4-fan condenser for moving

Step 1

Step 2

Step 3

Three-fan unit shown for illustration.

Method for 1-fan and 2--fan condensers is the same.

Attach sling to 4-fan condensers with eyebolts.

15

Image 19
Contents Liebert Air Cooled, Direct Drive Condensers Fan Speed Control 2-8 fan models only Three-phase voltage is only voltage available as standardExample DCDF165-Y On condensers with VFD Control, Lee-temp receivers,Table of Contents Operation System MaintenanceVariable Frequency Drive Product Description and FeaturesHead Pressure Control Types Fan SpeedSound Level Options Typical System ConfigurationsTransient Voltage Surge Suppression Option Lee-Temp Discharge Fan Speed and VFDSite Considerations Dimensions and Weights1067 mm See for typical condenser footprint dimensionsFour-Fan41-3/16 Condenser 1046mm Condenser footprint dimensions Operation and component accessSee for typical Typical condenser footprint-dimensions Piping connections for 6- and 8-fan Fan Speed Condensers Site Preparation Quiet-Line Models Condenser physical dataQuiet-Line Condenser Models Refrigerant Planning ValuesR-407C refrigerant required, approximate ReceiverPacking Material Equipment InspectionUnpacking the Unit Handling Unit on the SkidRemoving the Skid and Attaching Slings Step Attaching legs to a 6-fan or 8-fan unitAttaching sling to a 6-fan or 8-fan unit for moving Mounting the CondenserElectrical Supply Preparation Line Voltage Wiring50Hz condenser full load amp values 60Hz condenser dataLee-Temp receiver electrical data, 50Hz and 60Hz Low Voltage Control WiringLow Voltage Monitoring Wiring-TCDV Only Electrical ConnectionsDelta-Connected Power Supply Wye-Connected Power SupplyVFD Control Condensers Tcdv only Disconnect EMC Filter for Delta-Connected Power Electrical Field Connection Descriptions Electric service connection and fuse blockElectrical field connections for VFD control condensers Inspection and Installation Piping Guidelines Refrigeration Piping ConnectionsVFD and Fan Speed Control condenser piping Field Piping InstallationLee-Temp head pressure control condenser piping General arrangement-Air cooled models with Lee-Temp control Single Circuit ShownSystem Dehydration/Leak Test and Charging Procedures Other Moving and Placing EquipmentElectrical PipingStartup Startup ChecklistSystem Maintenance General ProceduresHow to Clean Special ProceduresCondenser Cleaning When to CleanFan Motors Maintenance Inspection ChecklistMonthly Semiannually Condenser Condenser Electrical Panel Condenser Electric PanelSymptom Possible Cause Check or Remedy TroubleshootingSystem Maintenance System Maintenance Page That Ne tIti Ti n