3.Piping and Connections

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (Liquid Propane [L.P.] Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance BTUs being supplied.

The dryer is provided with a 1” N.P.T. inlet pipe connection extending out the back area of the burner box. The minimum pipe size connection (supply line) to the dryer is 1” N.P.T. For ease of servicing, the gas supply line of each dryer must have its own shutoff valve.

The size of the main gas supply line (header) will vary depending on the distance this line travels from the gas meter or, in the case of L.P. gas, the supply tank, other gas-operated appliances on the same supply line, etc. Specific information regarding supply line size should be determined by the gas supplier.

NOTE: Undersized gas supply piping can create a low or inconsistent pressure, which will result in erratic operation of the burner ignition system.

Consistent gas pressure is essential at ALL gas connections. It is recommended that a 1-inch (2.54 cm) pipe gas loop be installed in the supply line servicing a bank of dryers. An in-line pressure regulator must be installed in the gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches (29.9 mb) of water column (W.C.) pressure.

IMPORTANT: A water column pressure of 3.5 inches (8.7 mb) for natural gas and 10.5 inches (26.1 mb) for L.P. dryers is required at the gas valve pressure tap of each dryer for proper and safe operation.

A 1/8” N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural and L.P. gases must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid detergent works well).

WARNING: NEVER TEST FOR GAS LEAKS WITH A FLAME!!!

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (L.P. Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance BTUs being supplied.

IMPORTANT: The dryer and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

32

Image 36
Contents AD-115ES Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Cleaning Adjustments Lubrication Data LabelGas Models Only Electric or Steam Models Only Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASStandard SPECIFICATIONS/COMPONENT Identification SpecificationsPage Component Identification Page Installation Procedures Location RequirementsUnpacking and Setting UP Page This Exhaust Duct Transition Piece Must be Installed First Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements General Exhaust Ductwork InformationPage Page Page Page Page Page Page Electrical Information Electrical Service Specifications PER Dryer ADE-115ES 60 Kw Electric Oven Reversing, 3ø Motor ADE-115ES 72 Kw Electric Oven Reversing, 3ø Motor Page Page GAS Information 26.1 mb 27.4 mbPage Page Steam Information 689 kPa170.1 kg/hr Page Compressed AIR AIR Pressure Supply Page Preparation for Operation and START-UP Preoperational Tests Page Shutdown Instructions Basket Tumbler CoatingSERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Returning Warranty PartsPage Routine Maintenance CleaningSuggested Cleaning Schedule Clean the lint drawer or screen every third or fourth loadSteam Dryers Adjustments LubricationTroubleshooting No light emitting diode L.E.D. displayDrive motor is not operating does not start Blower motor is not operating does not start Microprocessor controller computer display reads dSFL Microprocessor controller computer display reads doorFailed microprocessor controller computer No heat for Steam Models only No heat for Electric Models onlyDryer operates but is taking too long to dry Condensation on main door glassDryer is making scraping noise at basket tumbler area Excessive noise or vibrationData Label Information Data LabelSerial Number Reversing Timer SPIN/DWELLADJUSTMENTS Timing LegendProcedure for Functional Check Replacement Components Page Page P O R T a N T ADC P/N114501