Quick Installation Guide
Rosemount 8712 / 8700 Series
Wafer Sensors
Gaskets
The sensor requires a gasket at each of its connections to adjacent devices or piping. The gasket material selected must be compatible with the process fluid and operating conditions. Metallic or
Figure 8. Wafer gasket placement
Spacer Installation
Horizontal meters Vertical meters
Alignment
1.On 1.5 through
2.Insert studs for the bottom side of the sensor between the pipe flanges and center the alignment spacer in the middle of the stud. See Figure 8 for the bolt hole locations recommended for the spacers provided. Stud specifications are listed in Table 3.
3.Place the sensor between the flanges. Make sure that the alignment spacers are properly centered on the studs. For vertical flow installations slide the oring over the stud to keep the spacer in place. See Figure 8. To ensure the spacers match the flange size and class rating for the process flanges see Table 4.
4.Insert the remaining studs, washers, and nuts.
5.Tighten to the torque specifications shown in Table 5. Do not overtighten the bolts or the liner may be damaged.
Table 3. | Stud Specifications |
|
|
| |
Nominal Sensor Size | Stud Specifications | |
0.15 | – 1 inch (4 – 25 mm) | 316 SST ASTM A193, Grade B8M Class 1 threaded mounted studs |
1.5 – | 8 inch (40 – 200 mm) | CS, ASTM A193, Grade B7, threaded mounting studs |
NOTE
Sensor sizes of 0.15, 0.30, and 0.5 in. mount between AMSE
13