TROUBLESHOOTING & REPAIR
MAIN TRANSFORMER REMOVAL & REPLACEMENT (continued)
FIGURE F.34 – CHOKE REMOVAL
CHOKE
| |
| (4) |
BOTTOM | GLASTIC |
"E" IRON | |
| STIFFENERS |
Return to Section TOC
Return to Section TOC
Return to Master TOC
Return to Master TOC
REMOVAL OF CHOKE AND TOP IRON ASSEMBLY
1.Remove the two (left and right) glastic stiffen- ers connecting the negative rectifier plate and choke assembly to the main transformer
2.Remove the top choke lead from the polarity selector switch or the negative output termi- nal.
3.Remove the bottom choke lead from the neg- ative rectifier plate.
4.Label and cut the choke thermostat leads.
5.Using the 9/16” deep well socket wrench, remove the four
6.Using a hoist, carefully lift the choke and top iron assembly out and clear of the trans- former coils.
NOTE: The coils may be “stuck” to the top iron and may require some careful prying to dislodge them. Depending upon which coil(s) are to be replaced, it may be advantageous to remove some of the “stuck” coils with the top iron.
7.The leads from the coils that are to be removed and/or replaced must be discon- nected. See the Wiring Diagram.
When aluminum leads are