Allied Air Enterprises 4HP16LT manual Evacuation

Page 11

to protect the manifold gauge set from damage caused by high pressure.)

2.With both manifold valves closed, connect the cylin- der of R410A refrigerant. Open the valve on the R410A cylinder (vapor only).

3.Open the high pressure side of the manifold to allow R410A into the line set and indoor unit. Weigh in a trace amount of R410A. (A trace amount is a maxi- mum of 2 oz. of refrigerant or 3 lbs. pressure.) Close the valve on the R410A cylinder and the valve on the high pressure side of the manifold gauge set. Discon- nect the R410A cylinder.

4.Connect a cylinder of nitrogen with a pressure regulat- ing valve to the center port of the manifold gauge set.

When using high pressure gas such as nitrogen for this purpose, be sure to use a regulator that can control the pressure down to 1 or 2 psig.

5.Adjust nitrogen pressure to 150 psig. Open the valve on the high side of the manifold gauge set to pressur- ize the line set and the indoor coil.

6.After a short period of time, open a refrigerant port to make sure that an adequate amount of refrigerant has been added for detection (refrigerant requirements will vary with lengths). Check all joints for leaks. Purge nitrogen and R410A mixture. Correct any leaks and recheck.

Evacuation

Evacuating the system of noncondensables is critical for proper operation of the unit. Noncondensables are defined as any gas that will not condense under temperatures and pressures present during operation of an air conditioning system. Noncondensables and water vapor combine with refrigerant to produce substances that corrode copper piping and compressor parts.

Low pressure gauge to suction line service valve

High pressure gauge to liquid line service valve

2.Connect micron gauge.

3.Connect the vacuum pump (with vacuum gauge) to the center port of the manifold gauge set.

4.Open both manifold valves and start vacuum pump.

5.Evacuate the line set and indoor unit to a minimum of 500 microns or lower. During the early stages of evacuation, it is desirable to close the manifold gauge valve at least once to determine if there is a rapid rise in pressure. A rapid rise in pressure indicates a relatively large leak. If this occurs, the leak testing procedure must be repeated.

6.When 500 microns or lower is maintained, close the manifold gauge valves, turn off the vacuum pump, and disconnect the manifold gauge center port hose from the vacuum pump. Attach the manifold gauge center port hose to a nitrogen cylinder with pressure regulator set to 150 psig and purge the hose. Open the manifold gauge valves to break the vacuum in the line set and indoor unit. Close the manifold gauge valves.

7.Shut off the nitrogen cylinder and remove the manifold gauge hose from the cylinder. Open the manifold gauge valves to release the nitrogen from the line set and indoor unit.

8.Reconnect the manifold gauge to the vacuum pump, turn the pump on, and continue to evacuate the line set and indoor unit until 500 microns is maintained within a 20-minute period after shutting off the vacuum pump and closing the manifold gauge valves.

9.When the requirements above have been met, disconnect the manifold hose from the vacuum pump. Open the service valves to break the vacuum in the line set and indoor unit.

WARNING

Do not use a compressor to evacuate a sys- tem. Avoid deep vacuum operation. Extremely low vacuums can cause internal arcing and compressor failure. Danger of equipment damage. Damage caused by deep vacuum operation will void warranty.

Use a thermocouple or thermistor electronic vacuum gauge that is calibrated in microns. Use an instrument that reads down to 50 microns.

1.Connect the manifold gauge set to the service valve ports as follows:

506468-01

Issue 1004

Page 11

Image 11
Contents 4HP16LT Series Fastener Torque Installation ClearancesTorque Table GeneralRoof Mounting Electrical WiringSlab Mounting Slab MountingWith Auxiliary Heat Thermostat DesignationsWithout Auxiliary Heat Brazing Connection Procedure Outside Unit Placement InstallationInstalling Refrigerant Line Refrigerant Line Sets Transition from Vertical to Horizontal Refrigerant Line Sets Installing Horizontal RunsR22 refrigerant will be used to flush the system Flushing Existing Line Set and Indoor Coil Flushing Connections Manifold Gauge Set Liquid and Suction Line Service ValvesRefrigerant Metering Device To Close Liquid or Suction Line Service Valve Service ValveBall Type Service Valve Valve Open To Open Liquid or Suction Line Service ValveEvacuation Refrigerant Charging Refrigerant Charge AdjustmentAmbient temperature Cooling Cycle Charge Using Weigh-In MethodBlocking Outdoor Coil R410A Temperature/Pressure ChartNormal Operating Pressures Approach Values for TXV Systems Check Charge Using Normal Operating PressuresFilter Drier OperationSensor Temp. / Resistance Range Defrost Board Pressure Switch ConnectionsDelay Mode Issue Defrost Control Board Diagnostic LEDs LED Description System Diagnostic ModuleInterpreting the Diagnostic LEDs Flash CodesShort Cycling 24VAC Power WiringMiswired Module Codes Miswired Module TroubleshootingThermostat Demand Wiring Maintenance Thermostat Operation Case of extended power outageHeat Pump Operation Preservice Check Sequence of Operation Start-Up and Performance ChecklistCooling HeatingSingle Stage Wire Diagram Two Stage Wire Diagram