Receiving, handling and storage

Heavy weight.

Improper lifting or hoisting can result in death, serious injury or property damage.

Obtain the services of a qualified rigger prior to hoisting the circuit breaker to assure adequate safety margins in the hoisting equipment and procedures to avoid damage.

Introduction

This portion of the instruction manual covers the receiving, handling and storage instructions for a type 38-3AH3 vacuum circuit breaker shipped separately from the switchgear. This section of the instruction manual is intended to help the user identify, inspect and protect the circuit breaker prior to its installation.

Receiving procedure

Make a physical inspection of the shipping container before removing or unpacking the circuit breaker.

Check for shipment damage or indications of rough handling by the carrier. Check each item against the manifest to identify any shortages.

Accessories such as the manual charging crank, the racking crank and the split plug jumper are shipped separately.

Shipping damage claims

Important: The manner in which visible shipping damage is identified by consignee prior to signing the delivery receipt can determine the outcome of any damage claim to be filed.

Notification to carrier within 15 days for concealed damage is essential if loss resulting from unsettled claims is to be eliminated or minimized.

1.When the shipment arrives, note whether the equipment is properly protected from the elements. Note the trailer number the equipment arrived on. Note also any blocking of equipment. During unloading, check the actual equipment delivered to verify it agrees with the delivery receipt.

2.Make immediate inspection for visible damage upon arrival and prior to disturbing or removing packaging or wrapping material. This should be done prior to unloading when possible. When total inspection cannot be made on vehicle prior to unloading, close inspection during unloading must be performed and visible damage noted on the delivery receipt. Take pictures if possible.

3.Any visible damage must be noted on the delivery receipt and acknowledged with the driver’s signature. The damage should be detailed as much as possible. It is essential that a notation "possible internal damage, subject to inspection" be included on the delivery receipt. If the driver will not sign the delivery receipt with the damage noted, the shipment should not be signed for by the consignee or their agent.

6

Image 6 Contents
Answers for energy Qualified person Table of contents Signal words Hazardous Procedures IntroductionIntroduction Field service operation and warranty issues IntroductionIntroduction Receiving procedure Receiving, handling and storageShipping damage claims Handling procedure Receiving, handling and storageOutdoor storage Storage procedureIndoor storage Space heatingInstallation checks and functional tests Inspections, checks and tests without control powerDe-energizing control power in switchgear Installation checks and functional tests Racking crank engagement procedure Type 38-3AH3 vacuum circuit breaker rackingPhysical inspections Manual-spring charging checkFinal mechanical inspections without control power Split-plug jumper connected to circuit breakerVacuum interrupter/ operator Vacuum interrupter/ operator Vacuum interruptersPhase barriers Primary disconnectsStored-energy operating mechanism Interrupter/operator module ConstructionCircuit-breaker pole Current-path assemblySwitching operation Vacuum interrupterType 38-3AH3 vacuum circuit breaker pole section Stored-energy operating mechanism Operating mechanism Auxiliary switchMode of operation Indirect releases tripping coilsClosing Use of manual-spring operation crankRapid auto-reclosing Trip-free functionalityOpening Manual operation62.2 62.5.2 50.3.1 53.0 Pawl roller 62.5.2 Close-latch pawl Vacuum interrupter/ operator Discharged Closing Standard Secondary shunt release optional Indirect releases dual-trip orUndervoltage optional 54.2Position a locked Capacitor-trip device Shock absorberSecondary disconnect Mechanism-operated cell MOC switch optional Truck-operated cell TOC switchShutter-operating linkage Secondary disconnect Shutters Circuit-breaker frame Trip-free interlockRating interlock Ground disconnectAlignment Racking mechanismVehicle function and operational interlocks Interlocks Circuit breaker racking-interlocksRacking interlocks Closed circuit breaker interlock Automatic closing-spring energy release Trip-free interlock position mechanical interlock Maintenance Introduction and maintenance intervalsMaintenance Recommended hand toolsRecommended maintenance and lubrication Inspection items and testsRemoval from switchgear Checks of the primary power pathCleanliness check Inspection of primary disconnects Maintenance and lubricationCircuit Number Checks of the stored-energy operator mechanismTypical for all three-phases Fastener check Manual-spring charging and contact- erosion checksElectrical-control checks Wiring and terminals checkAutomatic spring-charging check control power required Secondary-disconnect checkTypical vacuum interrupter contact curve Spring-charging motor checks Vacuum-interrupter mechanical checkVacuum-integrity check using dielectric test High-potential testsHigh-potential test voltages Field-test voltage Voltage Frequency withstandRating a Inspection and cleaning of circuit- breaker insulationContinuous Contact Functional testsCircuit-breaker overhaul Replacement at overhaulOverhaul Circuit breaker Number TypeVacuum interrupter replacement OverhaulSetting Vacuum interrupter replacement illustration Overhaul Checking the contact stroke Open the circuit breaker Hydraulic shock absorberMaintenance and troubleshooting Sub-assembly Inspect forMaintenance and troubleshooting Problem Symptoms Possible causes and remediesClosed Appendix Appendix Values Voltage Voltage range factor K3 Insulation Withstand Permissible tripping delay YMaximum design voltage Voltage levels Lightning-impulse BILRated Continuous4 Rated Maximum design voltageLevels Voltage levels Lightning-impulse BIL Short-circuit at rated maximum design voltage I5, 6Remarks Appendix