3 Gas connections

Connecting to gas supply

Verify that the appliance is supplied with the type of gas specified on the rating plate. This appliance is configured for operation up to 4,500 feet altitude. Consult factory for installations above 4,500 feet elevation.

Inlet gas pressure: Measured at the inlet pressure tap on the appliance gas manifold. The pressure tap is located upstream of the combination gas valve(s) (FIG. 3-3 on page 33).

See Table 3A for maximum and minimum inlet pressures. Do not exceed the maximum. Minimum inlet pressure is for the purpose of input adjustment.

TABLE 3A

INLET GAS PRESSURE

MODEL

NATURAL

 

LP

 

 

 

 

 

Max.

Min.

Max.

 

Min.

 

 

 

w.c.

w.c.

w.c.

 

w.c.

402 - 2072

14.0

4.5

14.0

 

8.0

 

 

 

 

 

 

Manifold pressure: The gas regulator on the unit’s combination gas valve is adjustable to supply proper manifold pressure for normal operation. See the Copper-fin II Service Manual for net manifold pressure settings.

If you must adjust regulator pressure, follow the instructions under Gas Manifold Pressure Adjustment in the Copper-fin II Service Manual. Do not increase regulator pressure beyond specified pressure setting.

Gas pressure test

Installation & Operation Manual

Install a manual main gas shutoff valve, outside of the unit gas connection within six feet of the unit in accordance with the requirements of the National Fuel Gas Code, ANSI Z223.1.

You must provide a sediment trap (drip leg) in the inlet of the gas connection to the unit.

 

NOTICE

It is the installer’s responsibility to supply

 

the sediment trap (drip leg).

 

 

Do not block access to the electrical cover

 

CAUTION

 

plate when installing the sediment trap.

 

 

 

 

The sediment trap must be a minimum of

 

 

12 inches from the appliance.

The combination gas valves have an integral vent limiting device and do not require venting to atmosphere, outside the building. The unit will not operate properly if the reference hose is removed or a vent to atmosphere is installed.

Optional gas controls may require routing of bleeds and vents to the atmosphere, outside the building when required by local codes.

Gas connection

All gas connections must be made with pipe joint compound resistant to the action of liquefied petroleum (L.P.) and natural gases. All piping must comply with local codes and ordinances. Piping installations must comply with approved standards and practices.

1.Make sure gas line is a separate line direct from the meter unless the existing gas line is of sufficient capacity. Verify pipe size with your gas supplier.

1.The appliance must be disconnected from the gas supply piping system during any pressure testing of that system at a test pressure in excess of 1/2 PSIG (3.5 kPa).

2.The appliance must be isolated from the gas supply piping system by closing a manual shutoff valve during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 PSIG (3.5 kPa).

3.The appliance and its gas connection must be leak tested before placing it in operation.

COUPLING

UNION

MANUAL MAIN

SHUT OFF

VALVE

USE WRENCH TO HOLD SUPPLY PIPE

12"

MIN

Gas piping

To safely operate this unit, you must properly size the gas supply piping. See Tables 3B through 3D for piping and fitting requirements. Gas pipe size may be larger than heater connection.

For ease of service, install a union.

NIPPLE

CAP

Figure 3-1_Gas Line Connection

If an inline high gas pressure regulator is NOTICE used, it MUST BE of the lockup type and

be located a minimum of 10 feet from the appliance. Failure to do so may result in insufficient gas volume supplied to the appliance.

31

Image 31
Contents Save this manual for future reference Models 402Contents Special instructions Please read before proceedingRemoval of Combustion Chamber Lining or Base Panels Owner warning Safety informationCopper-fin II How it works Copper-fin II How it works Copper-fin II How it works Copper-fin =B=R Rating RatingsFreeze protection Determine unit locationLocation of unit Indoor clearances from combustible constructionCombustion and ventilation air Outdoor boiler installationLocation Hydronic systems anti-freezeMinimum Recommended Combustion AIR Supply to Equipment Room Outside Combustion Air Using Direct VentingCombustion air filter Exhaust fansCAT I Negative pressure non-condensing VentingIdentify your appliance’s vent system CAT IV Flue pipe materialsDirect Vent see Venting support General informationBarometric damper location Common Venting Systems Conventional negative draft venting seeNegative draft Flue outlet pipingVertical vent termination clearances and location Masonry chimney installationsInspection of a masonry chimney 1Vent Termination from Peaked Roof 10 ft. or Less From Ridge Sidewall air inlet Vertical DirectAire venting seeCombustion air inlet piping Length of air inlet pipeCombined air inlet points Vertical Rooftop Air InletClearances Directaire Kits Model Horizontal KIT Vertical KIT Venting of flue productsSidewall vent termination clearances and location Sidewall venting seeSidewall with fan Sidewall venting terminationSidewall venting without fan Drain tee installationModels 402 Venting of flue products Horizontal DirectAire venting Powered Venting seeFlue outlet piping Direct venting seeVertical DV venting termination Combustion air inlet piping Masonry chimney installationHorizontal DV venting termination Horizontal Vent Termination Clearances and LocationSealing PVC, CPVC, ABS, dryer vent, and flex duct vent pipe Connecting the air inlet pipe to the unitAir inlet piping materials Length of air inlet pipeVertical Combustion Air Inlet Clearances Multiple sidewall direct vent installationsVertical and sidewall combustion air inlet Horizontal combustion air inlet clearancesOutdoor vent/air inlet location Outdoor installation seeOutdoor vent cap kit Gas connection Connecting to gas supplyGas connections Gas pressure testGas train and controls Combination gas valvesVenting of combination gas valves Checking gas supply pressure GAS Piping Size ChartHeat exchanger Water flow switchWater connections Inlet and outlet connectionsWater connections heating boilers only Heating boiler installationsRelief valve Piping of the boiler systemLTV Valve Kits Model LTV Valve KIT Minimum boiler water temperaturesLow Temperature Return Water Systems Low temperature bypass requirementsMaximum Flow for Heating Boiler Low system water volumeThree way valves in system Radiant floor and snow melt heating systemsDHW installation Temperature / pressure gaugeTypical heating boiler installations Installation with a chilled water systemDiameter GPM4Primary/Secondary Piping of Multiple Boilers Floor Drain Heating Supply Loop 6Primary/Secondary Piping with Buffer Tank AMP Draw Data Installation must comply withElectrical connections Boiler operating control moduleDHW Domestic Hot Water thermostat Line voltage connectionsEMS or remote thermostat connection Low voltage connectionsSystem supply sensor recommended use Louver proving switchAlarm contacts Louver relay4Low Voltage Field Wiring Connections Wiring of the cascadeStart-up Start the boiler Check thermostat circuitsCheck vent and air piping Placing the boiler in operation1Lighting Instructions Set DHW operation Configuration of the cascadeSet clock How the control module operates Operating informationGeneral How the appliance operatesProtection features Temperature controlOutdoor reset operation, if used boilers only Boiler temperature regulationCascade DAY Switching on Sequence DHW, Night Setback, and Ramp Delay operation with cascadeSequence of the cascade Operation Display Sequence of operationCopper-fin II control module MENU/EXIT Display Screen ENTER/RESET UpdownTo save parameters and exit programming Access modesInstaller UserStatus display screens Syssup ***F Inlet ***FInlet Open Inlet ShortedFAN Speed Unit Pump DelayDHW Pump Delay STG DemandMIX VAL POS ** % Operation of the cascadeMaximum Water Flow Temperature Rise AT Full Rate Fire 90 GPM FlowModel Temperature Rise F Domestic water heatersWater chemistry 1Typical Water Heater Piping with Storage Tank 2Single Water Heater Piping with Two Storage Tanks 3Multiple Water Heater Piping with a Single Storage Tank 4Multiple Water Heater Piping with Multiple Storage Tanks Ft. Hd Pump operationHeat exchanger Minimum Pump PerformanceMinimum water temperatures domestic hot water use Thermostat adjustment procedureDomestic water temperatures Location of Cold Water Supply Piping Connections Optional relief valveThermal expansion Cathodic protectionService technician Maintenance Maintenance and annual startupOwner maintenance Maintenance Ignition system checkout Check all wiringCheck control settings Check relief valve Inspect/replace hot surface igniterCheck flue gas passageways Inspect and clean burnerPerform start-up and checks Check burner flameReview with owner Inspect and clean the heat exchangerOiled bearing circulators Digital Harness Connection diagramSplay Ladder DiagramFlow Switch
Related manuals
Manual 44 pages 7.23 Kb Manual 44 pages 18.25 Kb Manual 44 pages 8.33 Kb

402 - 2072 specifications

The Lochinvar 402 - 2072 is a versatile and highly efficient boiler designed to meet the heating demands of modern residential and commercial applications. This model stands out due to its innovative technologies, advanced features, and a high level of reliability, making it an ideal choice for consumers looking for an enduring and economical heating solution.

One of the primary characteristics of the Lochinvar 402 - 2072 is its impressive energy efficiency. With an exceptional annual fuel utilization efficiency (AFUE) rating, this boiler ensures minimal energy waste, allowing homeowners and business operators to save significantly on their energy bills. The model incorporates advanced condensing technology that enables it to extract heat from the combustion gases, maximizing heat transfer and reducing emissions.

The Lochinvar 402 - 2072 is built with a robust stainless steel construction that enhances durability and resilience against corrosion and other environmental factors. This material not only prolongs the lifespan of the unit but also contributes to its outstanding thermal efficiency. Additionally, the boiler's compact design allows for flexible installation options, making it suitable for various spaces, including tight utility rooms and basements.

Equipped with a user-friendly control interface, the Lochinvar 402 - 2072 allows for easy monitoring and adjustment of settings. Its advanced digital display provides real-time data on system performance, ensuring the operator can maintain optimal performance and efficiency.

Another noteworthy feature is the unit's quiet operation. The design includes sound-dampening insulation and high-efficiency circulators, keeping noise to a minimum, which is an essential trait for both residential and commercial settings.

The Lochinvar 402 - 2072 is also designed with safety in mind. It incorporates multiple safety features including an automated vent damper, low water cutoff, and a comprehensive control system that monitors various operating conditions. This proactive approach to safety ensures that potential issues are identified and addressed before they become critical.

In conclusion, the Lochinvar 402 - 2072 boiler presents an exceptional combination of efficiency, durability, and user-friendly features. Its advanced condensing technology, stainless steel construction, and focus on safety make it a leading choice in the competitive boiler market, catering to the heating needs of a diverse range of applications while ensuring environmental responsibility. For those in search of a dependable and efficient heating solution, the Lochinvar 402 - 2072 is certainly worth considering.