BOILER

Inspection

It is recommended the boiler be inspected for excessive scale and lime build up on a quarterly basis. In hard water areas or for steamers heavily used, a more frequent interval should be used. This inspection consists of an internal examination and cleaning of the boiler, an examination of the two hanging descalers, and for lime build up on the water level probes. Also, a check of all boiler controls, including the pressure switches.

Periodic service must be performed as outlined in these procedures. See “WATER CONDITIONING” under “GENERAL”.

WARNING: READ AND FOLLOW THE INSTRUCTIONS ON THE CLR BOTTLE. USE PLASTIC OR RUBBER GLOVES TO AVOID SKIN CONTACT. IF CLR LIQUID COMES IN CONTACT WITH THE SKIN, RINSE WITH CLEAN WATER.

Clean-Out (All Boiler Models)

1.Turn steamer OFF and drain boiler.

2.Remove hand hole plate and gasket (top front) from the boiler by removing the nut and clamp, then tapping the cover lightly to free it while holding the cover stud. This prevents the cover from dropping into boiler.

3.Remove old descaler retaining springs if present.

4.With a wire brush, or equivalent, dislodge and remove all loose scale from boiler shell. The loose material must be either scooped from the boiler or flushed through the drain.

5.Check probe canister and float valve assembly (regenerated models) for a scale build up and clean as necessary.

6.Check drain hole for obstructions.

7.Inspect the condition of the descalers as outlined in this section and replace if necessary.

8.Mix the deliming solution according to the instructions for the chemical being used.

NOTE: Boiler water capacities vary between seven to nine gallons for both gas and electric models depending on the boiler size and BTU/KW rating.

NOTE: If deliming solution accidently comes in contact with steamer components, lightly rinse off with clean water.

A.Models with Blowdown Timer - Pour deliming solution into boiler shell. Proceed to step 9.

B.Models without Blowdown Timer - Turn off the incoming water supply. Turn the power switch ON to close the drain valve. Pour deliming solution into boiler shell. Proceed to step 9.

C.Models with Deliming Port Assembly - Before pouring deliming solution into boiler, clean the seating surfaces for the hand hole gasket and then install a new gasket. Position the hand hole plate and tighten down. Turn off the incoming water supply. Turn the power switch ON to close the drain valve. Open the deliming assembly valve and pour the deliming solution into the port. Close the deliming assembly valve and proceed to step 10.

9.Clean the seating surfaces for the hand hole gasket and then Install a new gasket. Position and tighten the hand hole plate.

Page 22 of 88

Image 22
Contents VL Boiler Base Series Convection Steamers Table of Contents VL Series Steamers Introduction Water ConditioningSpecifications ToolsGas Steamers Electric SteamersRegenerated Steam Powered Boiler Gas Powered Steam BoilerElectrically Powered Steam Boiler Steamer OperationAutomatic blowdown Direct Steam Powered CookerBoiler Blowdown and Steamer Shut off Manual blowdownStandard Automatic Prevent High Limit Pressure Switch Water Level Gauge AssemblyCycling Pressure Switch Power SwitchBoiler Pressure Gauge Handhole Cover AssemblyDelime Port Assembly Check ValveThermal Switch Load Compensator Compartment Power SwitchCooking Timer Cooking Light RedRemoval and Replacement of Parts VL Series Steamers Removal and Replacement of Parts Cooking Compartment Controls Component Configurations Solid State Water Level Gauge AssemblyWater Level Controls LOW Level CUT OFF and Differential Electro MechanicalBoiler Assembly High Limit Thermostat GAS Combination Control Valve Boiler Fill and Cold Water Condenser Solenoid ValvesDoor Screw Nut Compartment Gasket and Door Screw NUT, Door and BushingsGasket Door and BushingSteam Coil Heater ContactorsHeating Elements Boiler Clean-Out All Boiler ModelsInspection Deliming Only Models with Deliming Port Assembly Solid State Low level Cut-Off & Differential Control Water Level Controls TestElectro Mechanical Low level Cut-Off & Differential Control Water Level Probes Disassembly Compartment Pressure AdjustmentFill and Cold Water Solenoid Valves Boiler not Filling with Water Boiler Blowdown Drain Solenoid ValveOlder Models Boiler Slow to PressurizeNewer Models All Models With BoilerDirect Steam Models Inlet Water StrainerElectric Models Regenerated Steam Coil SteamersVL Series Steamer Service Procedures and Adjustments GAS Burners Air Shutter AdjustmentAutomatic Ignition Systems GAS Models Terminals Spark Ignition Control TestGAS Manifold Pressure Adjustment Direct Steam Models Regenerated Steam Older Models Heater ContactorsVL Series Steamer Service Procedures and Adjustments Thermal Switch Prevent Automatic Models Steam Gate Valves Electrical Operation Water Level ControlsSolid State Auxiliary Low Level Cut-Off Electro Mechanical Low level Cut-Off & Differential Control Electro Mechanical Auxiliary Low Level Cut-Off Sequence of Operation Initial Fill and PreheatVL Series Steamer Electrical Operation Cook Cycle Water Refill After Initial FillElectric Models Boiler Blowdown/drainCook Cycle Water Refill After Initial Fill Purposely Left Blank Manual Ignition, Standard Controls Electronic Ignition, Standard Controls Manual Ignition, CSD-1 Code Controls Electronic Ignition, CSD-1 Code Controls VL Series Steamer Electrical Operation Manual Ignition, Standard Controls VL Series Steamer Electrical Operation Electronic Ignition, Standard Controls VL Series Steamer Electrical Operation Manual Ignition, CSD-1 Code Controls VL Series Steamer Electrical Operation Electronic Ignition, CSD-1 Code Controls VL Series Steamer Electrical Operation Auto Blowdown, Standard Controls Auto Blowdown, Cal-Code Controls Auto Blowdown, Standard Controls contactor 1 std VL Series Steamer Electrical Operation Auto Blowdown, Standard Controls contactors 2 std VL Series Steamer Electrical Operation Manual Blowdown, Cal-Code Controls contactors 1 std aux VL Series Steamer Electrical Operation Auto Blowdown, Cal-Code Controls contactors 1 std aux VL Series Steamer Electrical Operation Auto Blowdown, Cal-Code Controls contactors 2 std aux VL Series Steamer Electrical Operation Manual Blowdown, Cal-Code Controls contactors 2 std aux VL Series Steamer Electrical Operation Standard and Cal-Code/CSD-1 Controls See Schematic and Wiring Diagrams Compartment Controls Manual Blowdown Older Models Auto Blowdown Older Models Schematic and Wiring Diagrams Compartment Controls Automatic Standard Manual Troubleshooting ALL ModelsContacts not closing to power boiler fill solenoid Schematic and Wiring Diagrams Symptom Possible Causes GAS Models onlyPilot not adjusted correctly. See Pilot

VL2GPS, VL3GPS, VL3GSS, VL2GSS, VL2GAS specifications

Vulcan-Hart is well-known in the commercial cooking equipment industry, providing durable and efficient products that cater to the needs of restaurants and foodservice operations. Their line of griddles, namely the VL3GAS, VL3GPS, VL3GMS, VL2GAS, and VL2GPS, showcases their commitment to high-quality performance and innovative cooking technologies.

The Vulcan-Hart VL3GAS is a gas griddle, featuring a robust stainless steel construction that ensures longevity and resilience in a bustling kitchen environment. It offers a smooth, hot cooking surface that allows for optimal heat retention and distribution, ensuring that food cooks evenly. With a 3/4-inch thick steel plate, it provides excellent thermal conductivity, making it ideal for high-volume cooking. This model is designed with easy-to-use controls, which makes it convenient for chefs to operate.

The VL3GPS model is a gas-powered griddle that comes equipped with a patented grease management system, which aids in maintaining a cleaner cooking environment. This system helps to separate grease from food and minimizes flare-ups, enhancing safety during cooking. Additionally, the griddle features a temperature control that allows chefs to set precise cooking temperatures, ensuring consistent results.

Moving to the VL3GMS, this model introduces increased versatility with its combination of gas and optional electric features. It’s tailored for establishments that require flexibility in their cooking strategies. The VL3GMS is also designed with a spacious cooking surface, making it suitable for preparing a wide array of dishes simultaneously.

The VL2GAS is a two-burner gas griddle that is specifically tailored for smaller kitchen operations or those with limited space. Its compact design does not compromise on performance, still providing a durable cooking surface and reliable temperature control. This model is ideal for smaller cafes or food trucks where space is at a premium.

Lastly, the VL2GPS complements the VL2GAS with its grease management system. This enhances hygiene and ensures that cooking remains efficient and safe. Both VL2 models offer easy startup and shutdown procedures, making them user-friendly for chefs working in fast-paced environments.

Overall, the Vulcan-Hart VL series griddles combine quality construction, innovative technology, and efficient design. Whether it’s the three-burner or two-burner options, these griddles meet the demands of commercial kitchens, providing reliable cooking solutions that serve the dynamic needs of the foodservice industry.