Roberts Gorden DAT100, DAT75, DAT90, DAT115 Heater Pressure Switch, See Page 21, Section

Page 46

DUALAIR® HEATING AND COOLING UNITS INSTALLATION OPERATION AND SERVICE MANUAL

16.5 Heater Pressure Switch

Pull off 3 way connector. Spring open plastic clips of mounting cradle. Replace with correct type of pressure switch for model. The pressure switches are colour coded for each pressure setting.

Carry out a commission after working on or changing a pressure switch.

See Page 21, Section 11.

WARNING

Carbon Monoxide Hazard

Use correct pressure switch specified for each model.

Use of incorrect pressure switch could cause unsafe condition.

Failure to follow these instructions can result in death or serious injury.

Pressure Switch

75

90

100

115

RG P/N

90439811

90439807

90439811

90439807

 

 

 

 

 

Colour Code

grey

brown

grey

brown

 

 

 

 

 

40

Image 46
Contents DualAir Page Roberts-Gordon, LLC Page Table of Figures Page Product Approval Clearances to Combustibles Heater SafetyInstaller Responsibility Corrosive ChemicalsLocation and Suspension All models Minimum Required Installation ClearancesCritical Considerations 3.1 Basic Information VentilationInstallation Clearances and Clearances to Combustibles Specifications 4.1 DAT Front View Left VersionGeneral Technical Data Table Model 100 115 Fan DataModel 100 115 2 DAT100 and 115 4 kW motor Handling Heater Installation 5.1 GeneralShelf Mounting and Suspension Air Intake Terminal Cover Flue Installation 6.1 Flue InstallationType B22 Appliance Flue ConversionControl Section & Upper Panel Vertical and Horizontal Flue Termination Type B22 Appliance AIR Supply Room Sealed InstallationOpen Flued Installation Building VentilationDuct resistance and design. Tel +44 0 121 Optional Heater Configurations 8.1 Distribution DuctDepartment for recommendations regarding 7700GAS Piping ConnectionsSee Page 17, .3 through Page 18, Section Wiring and Electrical InformationRemote Control ModelsNumber DAT Wiring Diagram See Page 20, SectionSite wiring connections shown DAT Site Connections at Main Circuit Board Commissioning Automatic Burner Control Box Sequence Commissioning the Gas Valve Combustion TestingCommissioning the Gas Valves Set Minimum PressureComplete the Commissioning Pressure SwitchTurning Off the DualAir Unit Instruction to the UserSee Page 7, .3 and Page 8, Figure Heater OperationCommon User Controls Combination Fan/Limit Thermostat Secondary Limit ThermostatSimple Fault Finding burner faults Burner Lockout Reset ButtonSimple Fault Finding Cooling Section OperationIf you smell gas Heat Exchanger Maintenance Burner Maintenance13.3 Fan/Motor Assembly Maintenance Servicing 13.1 Servicing InstructionsGas Control Valve Maintenance Burner Conversion Conversion Between Gases 14.1 GeneralGas Valves Conduct Commissioning procedure as shown on Page 21, Section Troubleshooting For Automatic Ignition Burner Systems Result in death or electrical shockTroubleshooting for Flame Supervision System StartTroubleshooting for Solenoid Valves Troubleshooting for Main FanTroubleshooting for Fan Contactor Conduct Commissioning procedure as on Page 21, SectionBurner Components Removal and Replacement PartsGas Valve Replacement all models Gas Valve Burner Compartment Burner InjectorsIgnition Electrode and Flame Probe Remove screws securing outlet flange to the flue adapter Heater Pressure Switch See Page 21, SectionCoil Pressure Switch Pressure SwitchesFilter Pressure Switch 16.7.1 S4563C Ignition ControlFan Motor Removal Fan Removal and Replacement BREAK-OFF Link Must be Removed Page Some objects can catch fire or explode when placed
Related manuals
Manual 52 pages 20.28 Kb