Desa TSTA-A(-HA), (V)DVF36 Lowest Listed Discharge Vent Cap Opening Minimum Gas, Clearance

Page 16

Venting Installation

Instructions

Continued

Note: Pay special attention to these installa- tion instructions for required clearances (air space) to combustibles when passing through ceilings, walls, roofs, enclosures, attic rafters, etc. Do not pack air spaces with insulation. Also note maximum vertical rise of the vent- ing system and any maximum horizontal offset limitations. Offsets must fall within the parameters shown in Figure 25.

2.Set the fireplace in desired location. Drop a plumb line down from the ceiling to the posi- tion of the fireplace exit flue. Mark the center point where the vent will penetrate the ceiling. Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof to the locating hole in the ceiling. Mark the center point where the vent will penetrate the roof. Drill a small locating hole at this point.

Lowest

Listed

Discharge

Vent Cap

Opening

8'

 

Listed

Minimum

 

Gas

X

Vent

12

 

 

 

Roof Pitch is

 

 

 

x 12 Listed

 

 

 

Clearance

H (Min.) Height from Roof

 

 

 

 

ROOF PITCH

 

H(Min.)

 

 

 

Flat to 6/12

 

1.0'

 

 

6/12 to 7/12

 

1.25'

 

 

Over 7/12 to 8/12

 

1.5'

 

 

Over 8/12 to 9/12

 

2.0'

 

 

Over 9/12 to 10/12

 

2.5'

 

 

Over 10/12 to 11/12

 

3.25'

 

 

Over 11/12 to 12/12

 

4.0'

 

 

Over 12/12 to 14/12

 

5.0'

 

 

Over 14/12 to 16/12

 

6.0'

 

 

Over 16/12 to 18/12

 

7.0'

 

 

Over 18/12 to 20/12

 

7.5'

 

 

Over 20/12 to 21/12

 

8.0'

 

Figure 25 - Vertical Vent Termination

Clearance

Flat Ceiling Installation

1. Cut a 12 1/2" square hole in the ceiling using the locating hole as a center point. The open- ing should be framed to 12 1/2"x12 1/2" inside dimensions, as shown in Figure 18 on page 13 using framing lumber the same size as the ceiling joists. If the area above the ceiling is an insulated ceiling or an attic, nail firestop from the top side. This prevents loose insula- tion from falling into the required clearance space. If the area above the ceiling is a living space, install firestop below the framed hole. The firestop should be installed with no less than three nails per side (see Figure 26).

2. Assemble the desired lengths of pipe and elbows necessary to reach from the fireplace flue up through the firestop. All connections must be sealed with high temperature silicone sealant as specified in the second warning statement on page 11. Be sure all pipe and elbow connections are fully twist-locked (see Figure 17, page 13).

3. Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in roof.) The 12 1/2" x 12 1/2" hole must be measured on the horizontal; actual length may be larger depending on the pitch of the roof. There must be a 1" clearance from the vent pipe to combustible materials. Frame the opening as shown in Figure 18 on page 13.

4. Connect a section of pipe and extend up through the hole. If an offset is needed to avoid obstructions, you must support the vent pipe every 3 feet. Use wall straps for this purpose (see Figure 24, page 15). Whenever possible, use 45° elbows instead of 90° elbows. The 45° elbow offers less restriction to the flow of the flue gases and intake air.

If area above is an attic, install firestop above framed hole.

If area above is a living space, install firestop below framed hole.

Figure 26 - Installing Firestop

16

www.desatech.com

56131-F

Image 16
Contents Peninsula Models VDVF36 Peninsula Model ShownTable of Contents Safety InformationSafety Information High traffic areas Dimensions Right Side Front ViewPre-Installation Preparation Location and space requirementsClearances Mantel ClearancesFraming Rough Opening for Installing General Venting Vent Termination ClearancesMinimum Clearances for Vent Terminations Installation Precautions Venting Installation InstructionsInstallation Planning Installation for horizontal termination Installing Vent System in a ChaseSnorkel 90º Minimum 12 Minimum 45º SnorkelMale Slots Female Locking Lugs Rigid Vent Pipe Vent Cap Wood ScrewConnecting Vent Cap with Horizontal Vent Pipe Venting with Two 90 Elbows Installation for vertical TerminationHorizontal Venting Flat Ceiling Installation Lowest Listed Discharge Vent Cap Opening Minimum GasClearance Min. Height from RoofCathedral Ceiling Installation Cathedral Ceiling Support Box InstallationVertical V Horizontal H 1 + Min Max 20 max Starter ElbowVenting with One 90 Elbow Vertical V Horizontal H Min Max 20 max Starter ElbowHigh altitude installation Parts list for Desa venting kits and componentsVertical Venting Desa 5/8 Pipe & Vent Kits Number Description01492 Dura Vent 5/8 Pipe & Vent Kits Number DescriptionScrews Wall Switch Installation InstallationElectrical Hookup for optional blower accessory Optional Wireless hand-held Remote Control Installation For Optional Fan Kit From Blower AssemblyRed White To ThermopoileGAS Line HOOK-UP Gas Supply Testing Installing Log SetOpen Close Left Back Front RightPilot/Electrode Assembly Adjustment Burner Flame AdjustmentDecorative Facing Burner RemovalOperating Guidlines Maintenance Instructions Louver AssemblyGlass Door Hearth Pan LogsCleaning and Replacing Glass Door For Your Safety Read Before LightingGlass Assembly Frame Retainer Screws Louver Assembly Operating FireplacePosition Indicator Flame Adjustment Knob Lighting InstructionsTo Turn OFF GAS To Appliance Gas Control KnobSpecifications Service HintsTechnical Service Parts Under WarrantyTroubleshooting Parts Not Under WarrantyProblem Possible Cause Remedy Millivolt systemTroubleshooting Electronic ignition systemWiring Diagrams GAS ValveSkytech Remote Control KIT Pilot AssemblyReceiver and HAND-HELD Replacement Parts Accessories High Voltage CableKeep this Warranty Warranty InformationLimited Warranty DIRECT-VENT Fireplace