Verona WALL HUNG GAS BOILER manual Exhaust Pipe Location, External Vent Surfaces Are Hot

Page 15
7. Exhaust Pipe Location

7. Exhaust Pipe Location

CAUTION

EXTERNAL VENT SURFACES ARE HOT.

IT IS RESPONSABILITY OF THE HOMEOWNER TO KEEP THE VENT

TERMINAL CLEAR OF SNOW AND ICE

NOTE: USE ONLY LISTED COMPONENTS SUPPLIED WITH THE BOILER. SURFACE DISCOLORATION OF THE BUILDING MAY OCCUR DUE TO IMPROPER INSTALLATION. QHT WILL NOT ACCEPT RESPONSIBILITY OR LIABILITY FOR SUCH DISCOLORATION.

The Exhaust Hood must be installed on the leeward side of house and conform to the following guidelines:

1.The Vent hood shall not be less than 3 feet above any forced air inlet to the house.

2.The Vent hood shall not be less than 4 feet below, 4 feet horizontally, or 1 foot above any door, window or gravity inlet into any building.

3.The Vent hood shall not be less than 2 feet from an adjacent building.

4.The Vent hood shall be not less than 7 feet above grade when located adjacent to public walkway.

5.The Vent hood shall be located so that flue gasses are not directed to jeopardize people, overheat combustible structures, materials or enter buildings.

6.Minimum of 4 feet horizontal clearance from electric meters, gas meters, regulators and relief equipment.

7.All joints in system are to be sealed to prevent leakage of products of combustion in the building.

8.Avoid installing exhaust hood on the North, West, or the side of the house receiving the prevailing winds.

RIVA HEAT ONLY MANUAL - REV A

15

Image 15
Contents Distributed By WHAT TO DO IF YOU SMELL GASDo not try to light any appliance Manufactured byRIVA HEAT ONLY MANUAL - REV A QHT inc Page Number Table of ContentsSection Title Section NumberPage Number Table of ContentsSection Title Section NumberDANGER WHAT TO DO IF YOU SMELL GASDo not try to light any appliance Symptoms of CO poisoning include the following IMPORTANT INFORMATION Please read this page carefullyCodes and Regulations Key Features 1. General Information2. Technical Information M130.30CR 2.Technical Information Cont Primary Components 3. Parts ListRIVA HEAT ONLY MANUAL - REV A 4. Internal Piping & Parts ListVerify proper operation after servicing 5. Electric DiagramsWARNING Do not install the boiler on carpeting 6. Installation Location7. Exhaust Pipe Location EXTERNAL VENT SURFACES ARE HOTTERMINAL CLEAR OF SNOW AND ICE 8. Mounting Bracket Restrictor Size 9. Venting9.1 Restrictor Sizing Coaxial 2.5/4.0Installation 9. Venting Cont9.3 Choice of flue Installation 9. Venting ContFigure 9.4 Twin pipe φ 3.25 in Installation 9. Venting ContFigure 9.5 Twin Pipe Φ 3.25 in Installation 10. Pipe Connections12. Electrical Connections/Wiring 11. Gas Pipe ConnectionsWARNINGS 12. Electrical Connections/Wiring Cont Removing Front Panel12.2Connection to the electricity supply 12.3 Room Thermostat Connection 12.4Relay Panel Connection12. Electrical Connections/Wiring Cont 12.6 Finishing 12.5 Zone Valve Micro Switch Connection13.2 Expansion vessel 13.Circulator Sizing14.1 Primary - Secondary Piping 14. Piping14.2Primary - Secondary Piping with Zone Valves 14.Piping ContGauge 14. Piping ContReturn Water Temperature15. Commissioning 15.1Initial filling of the system15.2 Lighting the boiler checks all of the test 15.Commissioning Cont15.3Checking the gas pressure at the burner Important after the15.4Adjustment of the gas pressure 15. Commissioning Cont15.5 Checking the ignition device Important after the 15.7 Adjustment of the useful c.h. output15.6 Checking the burner ignition 15. Commissioning Cont15.Commissioning Cont 15.8Labels placement15.Commissioning Cont 15.9Checking the flue system and combustion15.10Instructing the user Useful output16. Gas Conversion Procedures17.2 Dismanteling the external panels 17. Annual Maintenance17.4Cleaning the primary heat exchanger 17.1 Warnings17.8 Visual inspection of appliance 17. Annual Maintenance Cont17.6 Cleaning the burner 17.7 Checking the flueSystem Checkout 18. Installer Notes17962.1274.1 2906 40A4USA 1796212741