11. Gas Pipe Connections

11. Gas Pipe Connections

Gas supply piping is to be sized and installed properly in order to provide a supply of gas sufficient to meet the maximum demand without undue loss of pressure between the meter and the boiler. Consult with the National Fuel Gas Code ANSI Z223.1 for proper sizing of gas piping for various lengths and diameters.

Direction of flow

F

A

B

C

A)Manual T-handle Shutoff Valve

B)Pressure Gauge Port

C)Flexible Gas Line to Burner

D)Male Union ¾” NPT

E)Pipe Cap

F)1” X 1” X ¾” TEE

Note: Height of valve above ground level to conform to local codes, if any.

Massachusetts statecode requires gas shut off to be a tee handled gas cock.

E

D

Figure 11.1

Locate a drop pipe adjacent to, but not in front of the boiler. Locate a tee (F) in the drop pipe at the same elevation as the gas inlet connection to the boiler. Extend the drop line with a nipple towards the floor and cap to form a sediment trap (E). Install a shut off valve

(A)before the tee with sediment trap and a union after the tee before the combination gas valve (D).

When installing the boiler, make sure a pipe compound resistant to the action of liquefied petroleum is used. Check piping for leaks. Always check leaks with a water and soap solution.

The boiler and its individual shut-off valve must be disconnected from the gas supply piping during any pressure testing of that piping at test pressures in excess of ½ psi.

WARNINGS

DO NOT USE A FLAME FOR CHECKING GAS LEAKS

12. Electrical Connections/Wiring

RIVA HEAT ONLY MANUAL - REV A22

Image 22
Contents Manufactured by WHAT TO DO IF YOU SMELL GASDo not try to light any appliance Distributed ByRIVA HEAT ONLY MANUAL - REV A QHT inc Section Number Table of ContentsSection Title Page NumberSection Number Table of ContentsSection Title Page NumberWHAT TO DO IF YOU SMELL GAS DANGERDo not try to light any appliance Symptoms of CO poisoning include the following Please read this page carefully IMPORTANT INFORMATIONCodes and Regulations 1. General Information Key Features2. Technical Information M130.30CR 2.Technical Information Cont 3. Parts List Primary Components4. Internal Piping & Parts List RIVA HEAT ONLY MANUAL - REV A5. Electric Diagrams Verify proper operation after servicing6. Installation Location WARNING Do not install the boiler on carpetingEXTERNAL VENT SURFACES ARE HOT 7. Exhaust Pipe LocationTERMINAL CLEAR OF SNOW AND ICE 8. Mounting Bracket Coaxial 2.5/4.0 9. Venting9.1 Restrictor Sizing Restrictor Size9. Venting Cont Installation9.3 Choice of flue 9. Venting Cont Installation Figure 9.4 Twin pipe φ 3.25 in 9. Venting Cont InstallationFigure 9.5 Twin Pipe Φ 3.25 in 10. Pipe Connections Installation11. Gas Pipe Connections 12. Electrical Connections/WiringWARNINGS Removing Front Panel 12. Electrical Connections/Wiring Cont12.2Connection to the electricity supply 12.4Relay Panel Connection 12.3 Room Thermostat Connection12. Electrical Connections/Wiring Cont 12.5 Zone Valve Micro Switch Connection 12.6 Finishing13.Circulator Sizing 13.2 Expansion vessel14. Piping 14.1 Primary - Secondary Piping14.Piping Cont 14.2Primary - Secondary Piping with Zone ValvesTemperature 14. Piping ContReturn Water Gauge15.1Initial filling of the system 15. Commissioning15.2 Lighting the boiler Important after the 15.Commissioning Cont15.3Checking the gas pressure at the burner checks all of the test15. Commissioning Cont 15.4Adjustment of the gas pressure15.5 Checking the ignition device 15. Commissioning Cont 15.7 Adjustment of the useful c.h. output15.6 Checking the burner ignition Important after the15.8Labels placement 15.Commissioning ContUseful output 15.9Checking the flue system and combustion15.10Instructing the user 15.Commissioning ContProcedures 16. Gas Conversion17.1 Warnings 17. Annual Maintenance17.4Cleaning the primary heat exchanger 17.2 Dismanteling the external panels17.7 Checking the flue 17. Annual Maintenance Cont17.6 Cleaning the burner 17.8 Visual inspection of appliance18. Installer Notes System Checkout1796212741 17962.1274.1 2906 40A4USA