Verona WALL HUNG GAS BOILER Commissioning, 15.1Initial filling of the system, Lighting the boiler

Page 30
15. Commissioning

15. Commissioning

Remove the front panel of the case.

Unscrew the cap on the automatic air purger valve 3 (Fig 15.1) one full turn and leave open permanently.

3

2

Figure 15.1

Open the installer supplied automatic fill valve between the cold water inlet and Central Heating System (See 28 on piping diagrams in previous section).

15.1Initial filling of the system:

Open each radiator

air vent starting at the lower point and close it only when clear water, free of bubbles, flows out.

Purge the air from the pump by unscrewing the pump plug 2 (Fig. 15.2); release the pump by turning the rotor in the direction indicated by the arrow on the information plate.

2

figura 15.2

• Close the pump plug.

Continue filling the system. The actual reading should ideally be 1.3 bar (19 psi) and not less than 0.3 bar (4.3 psi).

Close all air release valves on the c.h. system.

Inspect the boiler and the system for water soundness and remedy any leaks discovered.

Cold flush the system to remove any loose particles and any system debris before starting the boiler for the first time.

Reassemble the front panel of the case.

Return fill valve to automatic position.

 

15.2 Lighting the boiler:

 

 

Note: If external controls are fitted (e.g. room thermostat) ensure they "call for heat".

 

• Turn on the electricity

seconds.

A

B C D

supply to the boiler,

• Turn the function

 

 

switching on the circuit

selector B as in Fig.

 

 

breaker switch. The

15.3. The appliance

 

 

appliance operation

operation light A will

Figure 15.3

 

light A will flash every 4

flash every 2 seconds.

 

The boiler will now go through an ignition sequence and the burner will light.

If during the ignition attempt period the boiler fails to light, the full sequence control p.c.b. will go to lockout and the lock-out signal lamp D will appear.

To reset the boiler turn the knob B (figure 15.3) on the 0 position and then press and release the boiler reset button C (Fig. 15.3).

RIVA HEAT ONLY MANUAL - REV A

30

Image 30
Contents Manufactured by WHAT TO DO IF YOU SMELL GASDo not try to light any appliance Distributed ByRIVA HEAT ONLY MANUAL - REV A QHT inc Section Number Table of ContentsSection Title Page NumberSection Number Table of ContentsSection Title Page NumberDANGER WHAT TO DO IF YOU SMELL GASDo not try to light any appliance Symptoms of CO poisoning include the following IMPORTANT INFORMATION Please read this page carefullyCodes and Regulations Key Features 1. General Information2. Technical Information M130.30CR 2.Technical Information Cont 3. Parts List Primary Components4. Internal Piping & Parts List RIVA HEAT ONLY MANUAL - REV A5. Electric Diagrams Verify proper operation after servicing6. Installation Location WARNING Do not install the boiler on carpeting7. Exhaust Pipe Location EXTERNAL VENT SURFACES ARE HOTTERMINAL CLEAR OF SNOW AND ICE 8. Mounting Bracket Coaxial 2.5/4.0 9. Venting9.1 Restrictor Sizing Restrictor SizeInstallation 9. Venting Cont9.3 Choice of flue Installation 9. Venting ContFigure 9.4 Twin pipe φ 3.25 in Installation 9. Venting ContFigure 9.5 Twin Pipe Φ 3.25 in 10. Pipe Connections Installation12. Electrical Connections/Wiring 11. Gas Pipe ConnectionsWARNINGS 12. Electrical Connections/Wiring Cont Removing Front Panel12.2Connection to the electricity supply 12.3 Room Thermostat Connection 12.4Relay Panel Connection12. Electrical Connections/Wiring Cont 12.5 Zone Valve Micro Switch Connection 12.6 Finishing13.Circulator Sizing 13.2 Expansion vessel14. Piping 14.1 Primary - Secondary Piping14.Piping Cont 14.2Primary - Secondary Piping with Zone ValvesTemperature 14. Piping ContReturn Water Gauge15. Commissioning 15.1Initial filling of the system15.2 Lighting the boiler Important after the 15.Commissioning Cont15.3Checking the gas pressure at the burner checks all of the test15.4Adjustment of the gas pressure 15. Commissioning Cont15.5 Checking the ignition device 15. Commissioning Cont 15.7 Adjustment of the useful c.h. output15.6 Checking the burner ignition Important after the15.8Labels placement 15.Commissioning ContUseful output 15.9Checking the flue system and combustion15.10Instructing the user 15.Commissioning ContProcedures 16. Gas Conversion17.1 Warnings 17. Annual Maintenance17.4Cleaning the primary heat exchanger 17.2 Dismanteling the external panels17.7 Checking the flue 17. Annual Maintenance Cont17.6 Cleaning the burner 17.8 Visual inspection of appliance18. Installer Notes System Checkout1796212741 17962.1274.1 2906 40A4USA