1.INSTALLATION
A.NOZZLE SYSTEM LAYOUT
(1)If a drawing for the proposed system was not supplied, then it is recommended that one be created prior to installing the system. With reference to the AIRFOG Engineering Manual, review the site where the nozzle system is to be installed. The location of equipment, lights, pillars and other structures should be drawn on the floor plans. The proper selection and location of the nozzles is very dependent upon these obstructions. Figure 1 Typical Nozzle Layout, can be used as a guide for identifying the various components used with a system.
(2)The supply and feed lines for the system should be kept in straight unobstructed lines where possible. Air and water distribution network pipes are to be installed level along walls, pillars or hung from the ceiling. Avoid placing the lines over top of equipment and other areas, which will make it difficult to gain access at a later date. If the lines have to be routed around an obstacle such as a beam, always go under the obstacle, never over it.