Nortec Industries Airfog Series installation manual Pilot Lines, Schematic Plumbing Layout

Page 26

M.PILOT LINES

(1)All air pressure lines connecting to the control panel must be 1/4” O.D. plastic tubing rated for 150 psig. Figure 16 Schematic Plumbing Layout illustrates the proper connections of the air supply to and from the control panel to the vacuum valve and the pilot air regulator. The control panel requires an input pneumatic (air) control supply, which is usually tapped off the main air supply line upstream of the pilot air regulator. The control panel has two pneumatic fittings located on its top plate; one marked “pilot in” and the other marked “pilot out”. The “pilot in” is connected to the control supply with the 1/4” plastic tubing. A second 1/4” line connects the “pilot out” to both the pilot air regulator and the vacuum valve using a “T” connector.

Figure 16. Schematic Plumbing Layout

10-10

Page 19 2008-04-11

Image 26
Contents Airfog SeriesTM Proprietary Notice Liability Notice Table of Contents SHUT-DOWN Procedure List of Figures List of Tables This page Intentionally Left Blank Introduction Introduction General Airfog Technical Considerations Older Nortec Airfog System Components 10-00 This page Intentionally Left Blank Installation Installation Nozzle System LayoutTypical Nozzle Layout for Wall Mounted System Multi Zone Layout Supply Feed Lines CleaningIntroduction Mounting of NozzlesWater and Air Line Pressure Control Connecting Nozzles Saddle Clamp InstallationVacuum Valve Pilot Operated AIR Regulator10-10 Vacuum Valve Operation Primary Water Pressure Control Electrical WiringPrimary AIR Pressure Control Control PanelPrimary Air Pressure Control Section Schematic Plumbing Layout Pilot LinesThis page Intentionally Left Blank Mini & Octo Installation AFE Self Contained Airfog Systems AFE Mini SystemsMini Installations Installation Procedure AFE Octo SystemsOcto Layout with Interfaces 10-20 Ceiling Mounting of Octo Four Octo Units with a Single Control Panel START-UP Procedure Compressed AIR Supply Water SupplySelf Cleaning Cycle Adjustment Setting the System for Normal Operation Capacity Output vs. Vacuum Valve Adjustment This page Intentionally Left Blank SHUT-DOWN Procedure 10-40AFE, MINI, and Octo Shut Down Procedures Maintenance 10-50Maintenance Unscheduled Maintenance 10-50 Troubleshooting 10-60Troubleshooting 10-60 This page Intentionally Left Blank Spare Parts 10-70Spare Parts Octo Exploded View Octo This page Intentionally Left Blank Item # Description QTY Vacuum Valve Exploded View Item # Description Octo Mini Standard Control Panel Exploded View AFE This page Intentionally Left Blank Warranty Authorized Agent